Correction Slips to
Indian Railway Permanent Way Manual,
1986
(Incorporated Upto C/Slip
No. 27)
NOW CORRECTION SLIP AVAILABLE
UPTO 96 DATED 22-07-2004
(View & Copy print for
updating by your Manual)
ADVANCE
CORRECTION SLIP No. 96 dated. 22-07-2004
A
new para 607(3) may be added of Indian Railway Permanent Way Manual-1986 to
read as under:-
Para
607(3) – The stability of trains against
derailment, depends upon several factors such as track geometry, vehicle
characteristics & state of their maintenance and speed of the particular
vehicle at relevant point of time etc. Rail wheel interaction is thus, a
complex phenomenon and therefore, safety tolerances for track alone cannot be
prescribed in isolation. With this in view, safety tolerances for maintenance
of track, have not been prescribed on Indian Railways. Each derailment case,
therefore, needs careful examination of all available evidence, in respect of
Track, Rolling Stock, speed and other factors considered relevant, to arrive at
the cause.
The provision and tolerances mentioned
in Para 607(2) and elsewhere in this Manual are with a view to maintain track
geometry for good riding comfort.
ADVANCE
CORRECTION SLIP No. 95 dated. 30-06-2004
The
existing para 826 (i) of Indian Railways Permanent Way Manual may be modified
to read as under:-
826
(i) – The contractor shall not start any work without the presence of railway
supervisor or his representative and contractors supervisor at site.
A new para 826 (vii) may be added to
Indian Railway Permanent Way Manual as under :-
826 (vii) – The Engineer in charge
shall approve the methodology proposed to be adopted by the contractor, with a
view to ensure safety of trains, passengers and workers and he shall also
ensure that the methods and arrangements are actually available at site before
start of the work and the contractor’s supervisors and the workers have clearly
understood the safety aspects and requirements to be adopted/followed while
executing the work.
There shall be an assurance register kept
at each site, which will have to be signed by both, i.e. Railway Supervisor or
his representative as well as the contractor’s supervisor as a token of their
having understood the safety precautions to be observed at site.
ADVANCE
CORRECTION SLIP No. 94 dated. 01-06-2004
The
existing para 410 (3) and 410 (4) of Indian Railway Permanent Way Manual may be
modified to read as under:-
410(3)
Speed over interlocked turnouts- Speed in
excess of 15 kmph may be permitted for straights of interlocked turnouts only
under approved special instructions in terms of GR 4.10.
In the case of 1 in 8.5, 1 in 12 and
flatter turnouts provided with curved switches, higher speeds as permitted
under approved special instructions may be allowed on the turnout side, provided
the turn-in curve is of a standard suitable for such higher speeds. While
permitting speed beyond 15 kmph, provisions of Para 410 (4) may be kept in
view.
The permissible speed on turnouts
taking off on the inside of the curve should be determined by taking into
consideration the resultant radius of lead curve which will be sharper than the
lead curve for turn outs taking off from the straight. 1 in 8.5 turnouts should
not be laid on inside of curves.
410
(4) Upgradation of speeds on Turnouts and Loops to 30 kmph
(a)
Length of Section
- Upgradation of speeds on turnout
should cover a number of contiguous stations at a time so as to derive a
perceptible advantage of the higher speed in train operation. The works
described below, should cover all the running loops on the stretch of line
taken up.
(i)
Turnouts – Speed,
in excess of 15 kmph, should be permitted on turnouts laid with ST or PRC
sleepers only. All turnouts on the running loops shall be laid with curved
switches, with minimum rail section being 52 Kg. All rail joints on these
turnouts should also be welded to the extent possible.
For different type of curved switches permissible speed are as under:-
1. 1 in 8.5 curved switch 15 kmph
2. 1 in 8.5 symmetrical 30 kmph
split with curved switches
3. 1 in 12 curved switch 30 kmph
(ii)
Track on running loop
– Speed in excess of 15 kmph, should not be permitted on running loops laid
with wooden sleepers. The minimum track structure on the running loop should be
90R rails laid as Short Welded Panels, M+4 density on PRC, ST, CST-9 sleepers
and 150 mm ballast cushion. Out of 150 mm total cushion, clean cushion of 75 mm
at least should be available. Proper drainage of the area should also be
ensured.
(iii)
Turn-in-curves
– Speed in excess of 15 kmph, should not be permitted on Turn-in curves
laid with wooden sleepers. Turn-in-curves should be laid with the same rail
section as on the turn-out with PRC, ST or CST-9 sleepers with sleeper spacing
being 65 cm centre to centre (maximum).
Turn-in curve should conform to Para 410 (2) of IRPWM and especially so in respect of curvature of the lead curve.
Extra shoulder ballast of 150 mm
should be provided on outside of the turn-in curve.
The frequency of inspection of turn-in
curves should be same as that for main line turn-outs.
(b)
The following should
be ensured, if CST-9 sleepers are used in running loops or turn in curves:-
(i)
There is no cracks or fracture at rail
seat in two consecutive sleepers.
(ii)
There is no excessive wear of lug and
rail seat.
(iii)
All the fittings keys, cotters and tie
bars are fitted properly. Rail is held firmly with sleepers.
(iv)
Tie bars should not be broken or
damaged by falling brake gear, wagon parts etc. and they should not have
excessive corrosion or elongated holes. The corrosion of tie-bars inside the
CST-9 plate should be especially checked as this results in their removal and
adjustment becoming difficult.
(c)
The following should
be ensured, if ST Sleepers are used in Turnouts, Turn-in curves or running
loops:-
(i)
There is no crack or fracture at rail
seat in two consecutive sleepers.
(ii)
There is no excessive wear of lug, MLJ
and rail seat.
(iii)
All the fittings are effective and rail
is held with sleepers properly.
(iv)
The sleepers and fittings do not have
excessive corrosion, elongated holes etc.
ADVANCE CORRECTION SLIP No. 93
dated. 05-03-2004
The following correction may be made in advance correction slip nos.
32, 44 & 70 issued from Board to IRPWM – 1986:
Corrigendum to advance correction slip No. 32 dated. 04-08-1999:-
The existing para 320 (3) (5) Annexure 3/1
and para 320 (3) (8) Annexure 3/2 to be renumbered as Annexure 3/2 and 3/3 in
place of Annexure 3/1 and 3/2 respectively.
Corrigendum to advance correction slip No. 44 dated. 10-02-2000:-
The first line of
advance correction slip No.44 – The existing para 919 be replaced with
following should be replaced with “the existing para 919 (1) be replaced with
the following” respectively.
Corrigendum to advance correction slip No. 70 dated. 24-05-2001:-
The existing Note (1)
Annexure –DTM/1 regarding “scattered renewals, creep adjustments and earth work
repairs should be done as necessary” is deleted.
ADVANCE CORRECTION SLIP No. 92 Dated. 04.02.2004
The existing para 302
(1) (e) may be renumbered as para 302 (1) (f) para-302 (1) (e) be read as under
:-
Para-302 (1) (e)
– The service life in terms of total GMT of traffic carried for considering
through rail renewal on the bridge proper and in approaches (upto 100 m on
either side) for all the important bridges and such of the major bridges where
height of bank is in excess of 4.0 m, all tunnels and their approaches (upto
100 m on either side) shall be half of the GMT specified in para 302 (1) (d)
above.
The released P.Way
material shall be dealt with in accordance with para 320 of IRPWM.
ADVANCE CORRECTION SLIP No. 91 Dated. 20.01.2004
The existing contents of
para 252 (3) along with annexure 2/9 of Indian Railway Permanent Way Manual,
1986 may be deleted and substituted with the following:
Para
252 (3) – “ Ultrasonic testing of rails is specialized activity and the
inspectors carrying out the ultrasonic testing of rails shall be trained by
RDSO, in the technique of USFD testing. Each zonal railway shall create
adequate number of ex-cadre posts of inspectors to ensure that entire track
length in their jurisdiction is ultrasonically tested at the laid down
periodicity.
Detailed instruction for ultrasonic
testing of rails and welds are contained in the Manual for Ultrasonic Testing
of Rails and Welds, August, 1998, which along with its correction slips may be
referred to as Annexure to this Manual. It is very important that instructions
contained therein are carefully studied by the Permanent Way Officials
connected with the laying and maintenance of track”.
ADVANCE CORRECTION SLIP No. 90 Dated. 23.12.2003
The
existing para 421 of Indian Railway Permanent Way Manual may be modified to
read as under:
Para 421 – Criteria for realignment of a
curve:
(1)
When as a result of inspection by trolley or from the foot plate of
locomotive or by carriage or as a result of Track Recording carried out, the
running on a curve is found to be unsatisfactory the curve should be realigned.
(2)
The running over a curve depends not
only on the difference between the actual versine and the designed versine but
also on the station-to station variation of the actual versine value. This is
because it is the station to station variation of versine which determines the
rate of change of lateral acceleration, on which depends the riding comfort.
Service
limit for station to station versine variation for 3 speed group viz. 120 Km/h
and above, below 120 Km/h and below 80 Km/h and upto 50 Km/h, should be
considered as tabulated below:
|
Speed Range |
Limits of station to station Variation (mm) |
|
120 Kmph and above |
10 mm or 25% of the average versine on circular curve
whichever is more. |
|
Below 120 Kmph and upto 80 Kmph. |
15 mm or 25% of the average versine on circular curve
whichever is more. |
|
Below 80 Kmph and upto 50 Kmph. |
40 mm or 25% of the average versine on circular curve
whichever is more. |
In case exceeding of the above limit
is observed during an inspection, local adjustments may be resorted to in cases
where the variation of versine between adjacent stations is only at few
isolated locations, at the earliest possible. If more than 20% of the stations
are having versine variation above the limits prescribed, complete realignment
of the curve should be planned within a month.
The existing para 211(1) (v) of Indian
Railways Permanent Way Manual may be modified to read as under:
Para 211(1) (v) – The permanent way track diagram of the railway
line showing the type of track and fittings when laid, type of ballast, type of
formation with classification of soil (to be carried out as per RDSO’s Circular
No. GE-P1 – May 2003), blanket thickness, type of formation trouble (if any)
and indication of how the railway boundary is demarcated. Change points in the
track diagram shall be indicated correct to the nearest meter (details as in
annexure 2/4 (Revised)).
ADVANCE CORRECTION SLIP No. 88 Dated. 15.09.2003
The existing para 250 (2) (a) of
Indian Railways Permanent Way Manual may be modified to read as under:
(2)
Prevention of corrosion (anti corrosive measures) – (a) Anti corrosive painting
i)
Anti-corrosive painting of rails should be carried out in locations which are
prone to corrosion.
ii)
While carrying out renewals in these areas, anti-corrosive treatment should be
given before the rails are laid in the track.
The rust is removed and scales are loosened by wire
brushing/scraping. Thereafter rails are
painted with –
One
coat of red oxide zinc chromate primer to IS:2074.
Two
coats of Bituminous Emulsion to IRS-P-30-1996 to a dry film thickness of 350
microns (each coat to a minimum thickness of 175 microns).
iii)
In the case of rails that are already laid in track and subject to corrosion
the rails should be given the treatment in the track itself. The rust and scales are first removed by
wire brushes and thereafter painted with –
One
coat of red oxide zinc chromate primer to IS:2074.
Two coats of Bituminous Emulsion to IRS-P-30-1996 to a dry film
thickness of 350 microns (each coat to a minimum thickness of 175 microns).
ADVANCE CORRECTION SLIP No. 87 Dated. 25.07.2003
The existing para 170
(6) of Indian Railway Permanent Way Manual may be replaced as under:
170 (6) (a) - Where the beat of a keyman consists of PRC
sleeper- The Keyman should ensure that, in addition to his normal duty of
inspection and tightening of fitting, he should also carry out in a systematic
manner from one end, greasing of the ERC and eyes of inserts at the rate of 20
sleepers per day. Greasing shall be done as per the procedure laid down in para
1411 (5) (b) of IRPWM.
170 (6) (b) – Where the beat
of a keyman consists of PRC as well as other types of sleepers, SE(P.Way)
should make roster of keyman on monthly basis in the proportion of the beat, so
that work mentioned in para 170(5) and 170 (6) (a) are completed in respective
length. On any particular day however, he will do duties either as per 170 (5)
or 170 (6) (a) only.
ADVANCE CORRECTION SLIP No. 86 Dated. 07.07.2003
The
existing para 507 (1) of Indian Railways Permanent Way Manual may be modified
to read as under:
Para 507 Condition
of laying: (1) Alignment – SWR shall not be laid
oncurves sharper that 500 metres radius in both Board Gauge and Metre
Gauge. However, on PSC Sleepers, SWR
may be laid on curves with radius not less than 440 meters.
Existing
SWR laid on sharper curves may, however, be allowed to continue if there is no
difficulty experienced in maintaining these lengths. Chief Engineer’s approval should be taken in such cases.
ADVANCE CORRECTION SLIP No. 85 Dated. 13.05.2003
The
existing para 256 (1) of Indian Railway Permanent Way Manual may be replaced as
under:
(1)
(a) Permanent closure in running lines
should not be less than 5.5 metre in length.
However, for locations such as 500 metre length on both side approaches
of tunnels, tunnel proper, major and important bridges including bridge proper,
deep cutting and high embankments, the stipulations of para 1 (b) below shall
apply.
(1)
(b) Permanent closure in running lines, on
locations specified in para 1 (a) above, should not be less than 11 metre in
length, between two adjoining fish plates.
The closure rails existing in track
which are less than 11 metre, should be welded at least of 11 metre between two
adjoining fish plated joints. Till such
time this welding is done and the length of at least 11 metre is achieved,
speed restriction of 30 kmph shall be imposed.
ADVANCE CORRECTION SLIP No. 84 Dated. 08.05.2003
The
existing para 170(6) of Indian Railways Permanent Way Manual may be replaced as
under:
170
(6) (a) - Where the beat of keyman does
not consist of PRC sleepers – The Keyman should ensure that, in addition to his
normal duty of inspection and tightening of fittings, he proceeds in at least 3
T.P.lengths are made perfect every day, with a view to complete the beat in a
month.
170 (6) (b) - Where
the beat of a keyman consists of PRC sleepers – The Keyman should ensure that,
in addition to his normal duty of inspection and tightening of fittings, he
should also carry out in a sysmatic manner from one end, greasing of the ERC
and eyes of inserts at the rate of 20 sleepers per day. Greasing shall be done as per the procedure
laid down in para 1411 (5) (b) of IRPWM.
170 (6) (c) - Where
the beat of a Keyman consists of PRC as well other types of sleepers, the work
at (a) and (b) above, shall be done in respective lengths.
Existing para 1411 (5) (b) may be replaced as
under:
(b) Lubrication
of ERCs – Grease Graphite to the specification IS-408-1981 Gr. O should be used
for this purpose. This work should not
be carried out during extreme of summer and heavy rainfall. At a time ERCs should not be removed from
more than one sleeper. If for any
reasons mass lubrication of ERCs is taken up, at least 15 sleepers shall be
kept intact between any two sleepers taken up for lubrication of ERCs at the
same time. The ERCs should be cleaned
by wire brush and emery paper. The eye
of the insert shall also be cleaned by suitable brush. After cleaning, grease graphite shall be
applied to the inside surface of eye of insert and leg of ERC. Inside/Outside ERCs should be interchanged
and fixed again.
A new para 1411 (5) (c) be added to read as
under:
(c) The
lubrication of ERCs and insert at the time of intial laying should be done 100%
and thereafter should be done once in a year in corrosion prone areas &
platform lines and once in two years on other areas.
ADVANCE
CORRECTION SLIP No. 83 Dated. 25.2.2003
The existing para 606 of Indian
Railways Permanent Way Manual be modified to read as under:
606. Frequency of Track Recording - Track geometry monitoring of Metre Gauge routes
is not to be done by track recording car.
The Board Gauge routes should be monitored by TRC as per the following
frequencies (except for the routes where track recording is to be dispensed
with) :-
i) Routes with existing speeds above 130
kmph - Once in 2 months
ii) Routes with existing speed above 110
kmph and- Once in 3 months
upto 130 kmph.
iii) Other Group ‘A’ and ‘B’ routes - Once in 4 months
iv) Group ‘C’, ‘D’ and ‘D spl.’ Routes - Once in 6 months
v) Group ‘E’ and ‘E spl’ routes - Once in 12 months
ADVANCE CORRECTION SLIP NO. 82 Dated 10.02.2003
The existing para 1122 (4) (iii) of
Indian Railway Permanent Way Manual be modified to read as under:
(iii)
– The rail dolley shall be protected by a flagman at a distance of 1200 metre
on Board Gauge and 800 metre on MG/NG from the rail dolley, on a double line in
the direction on single line. The
flagmen shall also carry three detonators for use in any emergency.
ADVANCE CORRECTION SLIP No. 81 Dated. 03.12.2002
The existing para 914(b) (v) of Indian
Railway Permanent Way Manual be modified to read as under:
(v)
– Check rails of lavel crossing are required to be removed for tamping
operations, overhauling of level crossing, distressing of LWR or track renewals
etc. Check rails should be refixed as
quickly as possible and preferably before leaving site.
Should a situation arise where check
rails cannot be refixed for any reason and trains have to be passed, a speed
restriction of 30 kmph should be imposed besides ensuring that road traffic is
diverted till the check rails are put in place. In case such diversion is not possible, temporary arrangements
should be made for passage of road traffic till the check rails are put in
place. However, in both these cases,
the check rails should necessarily be provided latest by close of next
day. In such cases, a stationary
watchman shall be posted to ensure safety.
ADVANCE CORRECTION SLIP No. 80 Dated. 02.12.2002
New para may be inserted as 264(4) and
264(5) of the IRPWM – 1986 as mentioned below:
Para
264 (4) – In new line construction, ballast requirements will be assessed as
per the profile (to be adopted) given in para 263(I).
Para
264 (5) – The quantities assessed vide sub-para in (2), (3) and (4) above will
be the net quantities of ballast required to recoup the deficiencies or to
provide required profile/section. The
above net quantities may be enhanced suitably (say 8%) to arrive at gross
quantities of ballast for the purpose of procurement action in case
measurements are proposed to be taken in stacks or in wagons at originating
station.
ADVANCE CORRECTION SLIP No. 79 Dated. 10.10.2002
The following may be
replaced in suppression of Advance Correction Slip No. 71 dated. 17.7.2002 Para
283 (2) (c) of IRPWM – 1986 to read as under:-
(c) “No part of the tree shall be nearer than
4 mts from the nearest live conductor.
Any tree or branches likely to fall on the live conductor should be cut
or trimmed periodically to maintain the safety clearances. The responsibility for wholesale cutting of
the trees, i.e. cutting of tree trunks, will rest with the Engineering
Department. In the electrified
territories, however, the cutting of the trees shall be done by the Engineering
Department in the presence of authorized TrD staff to ensure safety and
satisfactory completion of the work.
The day-to-day trimming of the tree branches, wherever required, to
maintain the 4 m safety clearances from OHE shall be done by the authorized TrD
staff and Supervisors.
In case of dispute, the decision whether to cut
or trim a tree, shall be taken through a joint inspection of Engineering and
Electrical officials.
The
modalities to be adopted for cutting/trimming of the trees i.e. contractually
or departmentally, may be decided by the respective departments basedon local
conditions. Accountal and disposal of
treescut wholesale will be done by the Engg. Deptt. while the disposal of the
trimmed tree branches will be the responsibility of the TrD Department. The expenditure for cutting/trimming of
trees to maintain safe clearance for OHE, shall be debited to revenue grant of TrD
Department.”
ADVANCE CORRECTION SLIP No. 78 Dated. 09.09.2002
For Off-track tampers, the working instructions,
issued by Railway Board/ RDSO as amended from time to time, should be followed.
As an interim measure, where Off-track tampers are not
available, the packing may be done with the help of Crow bar/Beater, duly
taking care that the concrete sleepers are not damaged.
ADVANCE CORRECTION SLIP No. 77 Dated. 12.08.2002
(a) Broad
Gauge :- The following minimum rail
sections are recommended based on the speeds obtainable and the traffic
condition :-
|
Routes |
||||||||
|
Traffic
desnsity in GMT |
A |
B |
C |
D.Spl. |
D |
E.Spl. |
E |
|
|
More
than 20 |
60
Kg. |
60
Kg. |
60
kg. |
60
kg. |
60
Kg. |
60
Kg. |
60
Kg. |
|
|
10-20 |
60
Kg. |
60
Kg. |
60
Kg. |
60
Kg. |
52/90 |
60
Kg. |
52/90 |
|
|
5-10 |
60
Kg. |
52/90 |
52/90 |
52/90 |
52/90 |
52/90 |
52/90 |
|
|
Under
5 |
52/90 |
52/90 |
52/90 |
52/90
or 60 kg. (SH) |
52/90
or 60 Kg. (SH) |
52/90
or 60 Kg. (SH) |
*52/90
(SH) or 60 Kg. (SH) |
|
|
Loop
line |
52
Kg. IRS-T-12 second quality rails or 52 kg.(SH) |
|||||||
|
Pvt.Siding |
For
sidings with operating speed more than 80 kmph and upto 100 Kmph |
Track
structure specified for D route. |
||||||
|
For
sidings with operating speed more than 50 Kmph and upto 80 Kmph. |
Track
structure specified for E route. |
|||||||
|
Where
BOX’N’ or 22:1 Tonne axle wagon ply or operating speeds on sidings exceed 30
and are going upto 50 Kmph. |
52
kg. IRS-T-12 Second quality rails or 52 kg.(SH) |
|||||||
|
For
other sidings with operating speed upto 30 Kmph. |
52
kg. IRS-T-12 third quality rails also called ‘Industrial use rails’ or 52 kg.
(SH) |
|||||||
|
|
|
|
|
|
|
|
|
|
Note :- 52/90 represents 52 kg/90 UTS rail section.
(i) Existing
90 R rails may be allowed to remain for speeds not exceeding 110 Kmph.
(ii) On
routes identified for running of 22.1 Tonne axle load wagons, 60 kg. Rails
shall be used on all routes.
(iii) Head hardened rails
should be used on (a) Local lines where dedicated EMU stock is running. (b)
Ghat section with gradients steeper than 1 in 150 and/or curves sharper than 2
degree, (c) Locations where due to grades, curves, traffic density and type of
stock, the rate of wear of rails is such as to necessitate rail renewal, on
wear considerations, at a frequency of 10 years or so. (d) Routes where
predominantly captive rolling stock is moving in close circuit movement,
particularly with heavy mineral traffic. (e) The HH rails should be laid on
continuous and long stretches.
(iv) *Second
hand 52 kg. Rails may be used on case-to-case basis, with the prior approval of
Railway Board, depending upon quality of released rails available.
The
existing para – 322 of Indian Railways Permanent Way Manual be replaced to read
as under :-
322.
Identification of different qualities or rails in the Field –
(1) First
Quality Rails (T-12) – Indian Railways specification IRS-T-12/96 gives the
detailed specification of Flat Bottom Rails 60 kg. And 52 kg. Of grade 880 Mpa,
1000 Mpa and 1080 Mpa. 52 kg./m and 60
kg./m rails shall be classified as Class ‘A’ and Class ‘B’ rails based on
tolerance in End straightness. The rails shall have rolled on it, the rail
section, the Grade of steel, identification marks of the manufacturer, month
and last two digits of the year of the manufacture, process of steel making and
direction of rolling of rail.
(2) Second
Quality Rails – These are rails with relaxation in sectional tolerance as
provided in Amendment to IRS-T-12/96 but other wise conforming to T-12/96 in
all other respects. The identification of such rails will be one hole of 6 mm
dia, champhered at both ends, drilled at the center length of the rail and at
the moddle of the web. These rails shall be used only on loop lines/sidings
with speed restriction of 50 Kmph. These rails shall be painted with orange
colour on both sides of the web for a distance of 1 metre from each end, for
easy identification.
(3) Third
Quality Rails – In addition to above two qualities, third quality rails
supplied by Steel Plants are arising, particularly during the inspection of
rails while producing first quality rails as per IRS-T-12 specification. There
is no deviation in chemical composition or mechanical property in ‘Industrial
Use’ rails from that of IRS-T-12. The deviations exist only in tolerance in
surface defects, dimensions and straightness. These can be used in industrial
sidings where speeds are limited to 30 kmph in B.G. and 25 kmph in M.G.
The
identification of such rails will be one hole of 12 m dia., champhered at both
ends, drilled at the center length of the rail and at the middle of the web. A
marking ‘I.U’ in 18 mm, size shall be stamped on both end faces of rail. The
third quality rail shall be painted with white paint on end face of the flange
and on both sides of flange for a distance of 500 mm, from each end for
identification.
ADVANCE CORRECTION SLIP No. 76 Dated. 26.11.2001
|
S.No. |
Type of Turnout (B.G.) |
Permissible Speed |
|
1 |
1:8.5 curved switch 52/60 Kg. on PSC
sleepers |
15 kmph |
|
|
|
|
|
2 |
1:8.5 symmetrical split with curved
switches 52/60 Kg on PSC sleeper. |
30 kmph |
|
|
|
|
|
3 |
1:12 curved switch 52/60 Kg on PSC sleepers. |
30 kmph |
410 (4)
Upgradation of speeds on turn-outs
should cover a number of contiguous stations at a time. Before upgrading
the speeds on Turn-out beyond 15 km/hr, the track structure of loop lines
should be strengthened as prescribed.
ADVANCE CORRECTION SLIP No. 75 Dated. 05.03.2001
ADVANCE CORRECTION SLIP No. 74 Dated. 26.11.2001
a) For
all Bridges: (1) On the bridge approaches, sleepers with arrangement for fixing
guard rails should be provided for provision of guard rails as per para 275
above.
2) Full
complement of track fittings at bridge approaches up to 100 metres should be
provided to maintain required track geometry and effort should be made to
immediately recoup deficiency noticed, if any.
3) Rail
level of track in approaches of bridges
should be maintained, as per provision
of IRPWM – 1986 under respective para and dips in rail level immediately
after abutments should be avoided. The alignment and super elevation in case of
curved track should also be maintained as per
provisions of IRPWM – 1986 under respective para.
4) Rail
joints should be avoided within three metres of a bridge abutment.
5) In
case of LWR track, full ballast section as specified in LWR Manual should be
provided up to 100 metres from the abutment.
6) Switch
expansion joints should be provided at the bridge approaches in LWR/CWR track
as per provisions of LWR manual.
b)
For important and major bridges :- In addition to para (a) above, following
should also be provided.
1)
In case of CST-9 or wooden sleeper track, concrete/steel through sleepers with
elastic fastenings should be provided up to 100m/upto full breathing length
wherever LWR is provided in approach of bridge.
2)
On the bridge approaches, for a length of abut 100 metres, width of cess should
be 90 cm. Clear of full ballast section to maintain ballast profile. For
maintaining ballast section, suitable ballast retaining arrangement should also
be provided.
ADVANCE CORRECTION SLIP No. 73 Dated. 02.11.2001
The existing para – 170 (6) of Indian Railways
Permanent Way Manual may be modified to read as under :-
(6) Where the beat of a Keyman
consists of PRC sleepers, apart from his round of the beat, the keyman should
also carry out in a systematic manner from one end greasing of the ERC and eyes
of inserts at the rate of 20 sleepers per day. Greasing shall be done as per
the procedures laid down in para 1411 (5) (b) of IRPWM.
ADVANCE CORRECTION SLIP No. 72 Dated. 07.08.2001
The
existing para -1411 (5) (b) of Indian Railways Permanent Way Manual be replaced
to read as under :-
(b)
In Service maintenance : Lubrication of ERCs in
track should normally be carried out by keyman in a systematic manner from one
end to other at the rate of 20 sleepers (80 ERC) per day. This work should not
be carried out during extreme of summer and heavy rainfall. Grease graphite to
the specification IS-408-1981 Gr. O should be used for this purpose. At a time,
keyman should not remove ERCs on more than one sleeper. If for any reason mass
lubrication of ERCs is taken up then between any two sleepers taken up for
lubrication of ERCs at the same time, at least 15 sleepers shall be kept
intact. The ERCs should be cleaned by wire brush and emery paper. The eye of
the insert shall also be cleaned by suitable brush. After cleaning, grease
graphite shall be applied to the inside surface of eye of insert and leg of
ERC. Inside/Outside ERCs should be interchanged and fixed again. The
lubrication of ERCs and inserts at the time of initial laying should preferably
be done in base depot and thereafter should be done once in a year in corrosion
prone areas and platform lines and once in two years in other areas.
ADVANCE CORRECTION SLIP No. 71 Dated. 17.07.2001
The
existing para – 283(2) (C ) of Indian
Railways Permanent Way Manual be replaced with the following :-
( C ) No part
of a tree shall be nearer than 4 metres from the nearest live conductor. Any
tree or branches likely to fall on live conductors should be cut or trimmed
periodically to maintain this clearance. Cutting or trimming should be done by
authorized O.H.E staff.
ADVANCE
CORRECTION SLIP No. 70 Dated. 24.05.2001
Scattered
renewals, creep adjustments and earth work repairs should be done as necessary.
Para 245 (e) be
modified to read as under :
(e)
While doing casual/scattered renewals, priority should be given in
replacing unserviceable joint sleepers and unserviceable consecutive sleepers. Through sleeper renewals should be carried
out in continuous stretches and released sleepers after reconditioning should
be used for scattered renewals. New
sleepers should not be used in sidings.
If the percentage of
unserviceable sleepers becomes high, speed restrictions may have to be
imposed.
The
following be added to para 301(1):
(8) Scattered Renewal
The existing
sub-para 301(3) be renumbered as 301(4) and modified to read as under :
(4) Casual Renewal : In this case, unserviceable rails,
sleepers and fastenings are replaced by identical sections of serviceable and
nearly the same vintage or new track components. These are carried out in isolated locations of continuous but
small stretches. Such renewals are not
a part of normal maintenance operations and cannot be covered under scattered
renewals.
A
new para 301(3) be added to read as under :
(3) Scattered Renewal : In
this case, unserviceable rails, sleepers and fastening are replaced by
identical sections of serviceable and nearly the same vintage track
components. These are carried out in
isolated locations and not more than 10 rails and/or 250 sleepers in a gang
beat in a year. Such renewals are a
part of normal maintenance operations.
Note (I) Annexure – DTM/I be modified to read as
under :
Scattered renewals, creep adjustments and earth work
repairs should be done as necessary.
The following line
be added as end of the existing para – 252 (2) of IRPWM – 1986 :-
Such
an inspection on the important girder bridges and their approaches should be
done twice a year.
ADVANCE
CORRECTION SLIP No. 69 Dated. 23.05.2001
A new para no.826 be added to
Chapter-VIII of the IRPWM, 1986 to read as under :
826 Safe working of contractors - A large number of men and machinery are
deployed by the contractors for track renewals, gauge conversions doublings,
bridge rebuilding etc. It is therefore
essential that adequate safety measures are taken for safety of the trains as
well as the work force. The following
measures should invariably be adopted :
|
(i) |
The contractor shall not
start any work with the presence of railway supervisor at site. |
|
(ii) |
Wherever the road vehicles
and/or machinery are required to work in the close vicinity of railway line,
the work shall be so carried out that there is not infringement to the
railway’s schedule of dimensions. For
this purpose the area where road vehicles and/or machinery are required to
ply, shall be demarcated and acknowledged by the contractor. Special care shall be taken for
turning/reversal of road vehicles/machinery without infringing the running
track. Barricading shall be provided
wherever justified and feasible as per site conditions. |
|
(iii) |
The look out and whistle
caution orders shall be issued to the trains and speed restrictions imposed
where considered necessary. Suitable
flagmen/detonators shall be provided where necessary for protection of
trains. |
|
(iv) |
The supervisor/workmen
should be counseled about safety measures.
A competency certificate to the contractor’s supervisor as per
proforma annexed shall be issued by AEN which will be valid only for the work
for which it has been issued. |
|
(v) |
The unloaded
ballast/rails/sleepers/other P.Way materials after unloading along track
should be kept clear off moving dimensions and stacked as per the specified heights
and distance from the running track. |
|
(vi) |
Supplementary site
specific instructions, wherever considered necessary shall be issued by the
Engineer in Charge. |
Certified that Shri
__________________________________P.way supervisor of
M/s._________________________________has been examined regarding P.Way working
on __________________________work. His
knowledge has been found satisfactory and he is capable of supervising the work
safety.
ADVANCE
CORRECTION SLIP No. 68 Dated. 25.04.2001
The
Annexure 2/3 to para 206 of IRPWM be replaced with the Annexure 2/3 enclosed.
The new paras as indicated below be
added to the existing para 206 of IRPWM – 1986 :-
(4) Maintenance
attention given to the signaled loop lines and turnouts should be recorded on
the chart.
(5) Whenever
the gang equipments are checked by PWIs, the same should be recorded in gang
chart against the date on which such inspection is done. Inspecting officials should initial against
the date on the chart and also made suitable entries in gang diary.
(4) Six
months after the end of each year, the gang charts will be collected by the
PWIs and maintained as record. Thus,
for the overlapping period of six months, the gang will have two gang charts
with them. A six months record will
therefore always be available with the gang for reference. Normally, this record should be kept for at
least five years. When a particular
kilometer or section is under special observation, the record may be maintained
for a longer period at the discretion of P.Way officials.
Annex 2/3 to para 206
ADVANCE
CORRECTION SLIP No. 67 Dated. 24.04.2001
The para 1408 of Chapter XIV of IRPWM
be deleted and substituted with a new para 1408 as under :-
1408 Maintenance
of concrete sleeper track :
(1)
General
(a)
Concrete sleeper track should be maintained by heavy on-duty track
tampers.
(b)
An annual machine deployment programme shall be drawn by
zonal railway and be circulated to the divisions before the beginning of the
year.
(c) For spot attention/slack picking,
multi-purpose tampers and off-track tampers shall be used. Where off-track tampers are not available,
as an interim measure, the packing may be done with the help of crow bar/beater
duly taking care that the concrete sleepers are not damaged.
(d)
Pre-tamping, during tamping and
post-tamping attentions should be given to track as indicated in para 226. (For further details, Chapter 3 of Indian
Railways Track Machine Manual may be referred to ).
(2) Annual Systematic Attention
on PRC track
In addition to machine tamping, the
gangs will carry out annual systematic attention to track from one end of gang beat to the other during work
season. This will include –
(a) Examination
of rails, sleepers and fastenings including measurement of toe load of ERCs.
(b)
Inspection of and attention to insulated joints, switch expansion joints etc.
(c)
Packing of approaches of bridges, level crossings, breathing lengths of LWRs
and bad formation areas etc.
(d) Shallow screening of track ..
(e) Through
packing of track not maintained by machine, e.g. tracks not on PSC sleepers
including all running lines of the yards and pints and crossings in such
running lines.
(f)
Minor repairs to cess of bank.
(g) Boxing and
dressing of ballast.
(h)
Replacement of damage/missing rubber pads, liners and ERCs.
(3) Annual Programme of maintenance of PRC
track
The annual maintenance programme for
machine maintained concrete sleeper track would be as under :-
|
Period |
Work |
|
(a) Post monsoon attention : (
For six-seven months after end of monsoon) |
Immediately after end of monsoon,
attend to run down stretches in the entire gang length. Thereafter, the following schedule of work
shall be followed : (i)
Picking of slack 1-2 days in a week (ii) Remaining days shall be allotted
to : (a) Annual
systematic attention. (b)
Overhauling of level crossings. (c)
Destressing of LWRs. (d) Spot
renewals of rails, sleepers etc. (e)
De-weeding. (f)
Cold weather patrolling, etc. |
|
(b) Pre-monsoon attention : (For two months prior to onset of
monsoon) |
(i) Picking of slacks 1-2 days in a
week. (ii)Remaining days shall be allotted
to : (a) Cleaning
and repairs to side and catch water drains and cleaning of water ways. (b) Attention
to yard drainage. (c) Spot
renewals of rails, sleepers etc. (d) Shallow
screening of specified lengths. (e) Hot
weather patrolling. |
|
(c)
Attention during monsoon : (For 3-4 months) |
(a) Picking
of slacks as required. (b) Normal
track maintenance of yard lines. (c) Cleaning,
removal and loose boulders from cuttings and tunnels to ensure free flow of
water. (d) Monsoon
patrolling. (e)
Maintenance of side and catch water drains. (f)
Repairs to cess and bank. |
|
Note : |
(i) |
For maintenance schedule on LWR
track, special instructions in the LWR Manual should, in addition, be followed. |
|
|
(ii) |
Spot renewal of trails and sleepers
shall be done as per requirement any time of the year. |
|
|
(iii) |
Destressing of LWRs shall be done as
per requirement and schedule to be prepared by the PWI, as per provisions of
LWR Manual. |
|
|
(iv) |
Main tamping, pre and post tamping
works shall be done as per schedule of working of the tamper. PWI and AEN should be advised at least one
month in advance of the programme of the machine to enable them to complete
pre-tamping operations. |
|
|
(v) |
Lubrication of ERC’s shall be done by
Keyman throughout the year as per para 1411(5)(b) of the Manual. |
|
|
(vi) |
Oiling and greasing and visual
inspection of fish plated joints shall be done as per para 241 of the Manual. |
ADVANCE
CORRECTION SLIP No. 66 Dated. 30.03.2001
A
new Para 914 (b)(v) be added to chapter IX of IRPWM to read as under :-
Check rails of level crossing are
required to be removed for tamping operation, overhauling of level crossings,
distressing of LWR or track renewal etc.
Check rails should be re-fixed as quickly as possible and preferably
before leaving site. Should a situation
arise where check rails cannot be re-fixed for any reason and trains have to be
passed, a speed restriction of 30 kmph should be imposed besides ensuring that
road traffic is diverted till the check rails are put in place.
ADVANCE
CORRECTION SLIP No. 65 Dated. 01.03.2001
A new para 309 (A)
be added to read as under :
309(A) Project
report for tract renewal works : Systematic
and meticulous planning for various items of execution of track works is
essential for achieving quality, economy and timely completion of works. For every sanctioned track work e.g. CTR,
TSR, TRR, deep screening, bridge timber renewal, etc. a detailed project report
should be prepared. The report should
inter alia, cover the following aspects :
i)
Details of Work -
Pink book detail, scope of work, locational details, cost of estimate
particulars etc.
ii)
Existing track structure -
Inventory of existing tract structure including the rails, sleepers,
fittings, ballast quantity/deficiency in track, type width of formation and
other details should be taken as prescribed in P.Way diagram, details of level
crossings, bridges, electric fittings, curves, height of bank, cuttings, yards,
sidings, etc.
iii) Classification of track materials - During inventory of the existing track
structure by foot by foot survey, identification, classification and
colour making of existing track
materials as second hand and scrap would be done as provided in para 320 of
IRPWM. The classification should be
approved by the competent authority.
Action plan for stacking storage and disposal of the released materials
should be clearly indicated. Inventory
of existing track materials would normally be prepared jointly by the PWI of
the section and the PWI(Spl) for the renewal.
iv)
Proposed track structure - The proposed P.Way diagram of the affected
length should be prepared in the same format as done for the existing track
structure and incorporated in the project report.
v)
Existing/proposed gradient profile - The
levels of existing track should be taken at every 20 metres and a gradient
diagram prepared. Introduction of
vertical curves should be critically examined and the proposed profile of track
shown in red line indicating the proposed grades. Lowering of track should be avoided. Precise lift of track at girder bridges should be worked out and
a separate scheme developed for lifting of girders on each of the affected
bridges. Similarly, the magnitude of
lifting at level crossing should be worked out and indicated in the
report. Care should be exercised to
keep the road surface in one level on level crossings spanning to across
multiple tracks. This may require regarding
of adjacent lines too.
vi) Realignment of curves - All curves should be measured afresh and
slew worked out for realignment wherever necessary, keeping in the obligatory
points in view.
vii) Method of execution - The work should be executed “bottom
upwards” i.e. sequence of execution of works will be in the following order –
![]()
![]()
Formation Ballast Sleepers
Rails.
viii)
Formation :
a) Repair
and widening of cess : The project
report should indicate the requirement of and plan for widening of formation in
both banks and cuttings wherever necessary.
Provision of proper drains in cuttings should also be planned.
b) Formation
treatment : Areas needing formation
rehabilitation should be identified and a study for possible solutions and
method of execution of the rehabilitation scheme should form part of the
project report.
ix) Ballast -
The requirement indicating bifurcation of cess supply and depot supply
and the source and means of each should be spelt out clearly. Mode of providing ballast cushion i.e. deep
screening or raising should be identified along with sketches of cross sections
present and proposed. Sleeper renewal
would normally not be started unless adequate arrangements for supply of
ballast have been made.
x) Transportation
of P.Way materials - The mode of
transportation for various track components and unloading of rails and sleepers
in particular, at the work sites should be indicated in the project report.
xi) Welding
- The
complete details of welding requirements, the arrangements need to be made for
its execution whether departmentally or through contract should be clearly
indicated in the report.
xii) Renewal
of turnouts, bridge timbers, etc - The project report should cover the complete
details of turnouts, bridge timbers, level crossings, etc. where renewal is to
be carried out. Whether turnouts are to
be laid manually or by mechanized means, should be clearly brought out
indicating the arrangements made. The
report should also include the mode and agency for overhauling and relaying and
making up of road surface at the level crossings.
xiii) Use
of machines - The requirement of machines for renewal (if
machanised renewal is planned) deep screening ( if mechanized deep screening is
planned) and tamping/stabilizing and the duration for which the machines are
required should be indicated. The
machines that would be deployed should be identified and staff nominated. The planning for repair of machines at the
works site, supply of fuel and other consumables should be planned. The requirement of additional lines in the
existing yards for making base depot and arrangements made for the same should
be indicated in the report.
xiv) Contracts -
The contracts that are required to be entered into for various
activities of works and the activities, which are to be done departmentally,
should be spelt out. The planning for
deployment of staff/supervisors for execution at various activities should be
indicated.
xv) Material
Planning - The material requirement should indicate the
materials to be arranged by the headquarters and by the Divisions. Against each material, the proper
nomenclature and drawing number should be indicated. Rails nons. And sizes (including lead rails, check rails etc.),
sleepers (including specials), rails and
sleeper fastenings, switches and crossings, level crossing and bridge
sleepers and fittings, etc. should be fully covered. The consignee particulars and the destination, the mode of
transport should also be indicated.
xvi) Manpower Planning -
The requirement of manpower including the officers, supervisors, artisan
and other staff should be worked out with minute details. The arrangements made for camping of these
officials and mobilization should be reflected in the report.
xvii) LWR/CWR plans - For welding of rails
into LWR/CWR, the LWR plan should be got approved by the competent authority in
advance. Such plan should form part of
the project reports.
xviii) Requirement of speed restrictions, traffic
blocks and other material train - Planning
for execution of track renewal works should be such that the time loss on
account of speed restriction is minimal and is within the permissible
limits. The report should indicate
requirement of speed restrictions and traffic blocks together with
duration. The corridor for blocks is
required to be planned in consultation with the Operating Department and
accordingly reflected in the report after obtaining the approval of DRM. Arrangements made for various type of wagons
for transportation of ballast, sleepers, etc. together with requirement of
locomotives should be indicated in the report in consultation with Sr.DOM and
with the approval of DRM.
xix) Monitoring mechanism - The
list of all activities involved and the time estimation for each activities
should be worked out. These activities
should be sequenced and co-related in logical manner and network diagram
prepared using CPM method. The critical
activities should thus be identified.
These should form part of the project report.
xx) The detailed project report covering
the various points as mentioned above should be prepared as soon as the
approval of Board to include the works in FWP is conveyed to the Railways. These reports should be submitted to
headquarters for scrutiny and approval.
ADVANCE
CORRECTION SLIP No. 64 Dated. 05.01.2001
The para 901 of chapter IX of IRPWM –
1986 modified vide correction slip No. 35 dated 19-08-99 be re-modified to read
as under :
901
General Location: As far as possible, new Level Crossings may not be
located in busy station yards where heavy detention to the road traffic and
other operational problems are likely to be encountered. If
provision of Level Crossing is inescapable it may be located outside the
outermost facing points. For Level
Crossings already located within busy station yards affecting Railway
operations and causing heavy detention to the road traffic, efforts should be
made to replace them by road Over/ Under Bridges as per extant rules or shift
them outside the outer most facing points, especially during planning of gauge
conversions, yard re-modeling and doublings and iits operation
ADVANCE
CORRECTION SLIP No. 63 Dated. 27.11.2000
The
following para be added at end of the existing para 275(3) of IRPWM – 1986:-
The fixing of guard rail on
concrete sleepers shall be done as shown in drawing No. RDSO/T-4088 to 4097 by
proper tightening of ail screws.
Provision of MS flats/tie bars for tying PRC sleepers together at ends
is not required.
ADVANCE
CORRECTION SLIP No. 62 Dated.
The following line be added at the end
of the existing para-1405 of IRPWM 1986 :-
`For laying of concrete sleepers for
fan shaped turnout, the instructions given in para 1413 be followed.'
A new para 1413 be added to read as
under :
1413. Laying
of fan shaped turnout sleepers :
(1) Loading of PSC turnout sleepers in BFRs.
(a) Sleeper of the approach and sleepers meant
for lock bar crank will be loaded at right angles to the track.
(b) The remaining sleepers will be loaded
parallel to the track on the BFRs.
(c) Suitable nos. of wooden battens to support
the sleepers in between layers of turnout sleepers will be used as in case of
main line sleepers to prevent damage.
2. Unloading
:
(a) Depending upon the process of laying of
the turnout adopted, the sleepers shall be unloaded either near the proposed
location on firm & level ground or adjacent to a nearby siding or on a
goods platform by means of a crane.
(b) While unloading due care shall be taken
that the sleepers or the inserts are not damaged.
1.
Site preparation for laying :
(a) Ensure that a clean ballast cushion of 30
cm below the bottom of sleeper is available.
(b) These turnout sleepers are to be laid
where the approach track is also laid with PRC sleepers. Thus there would be no need to lower the
formation to provide adequate ballast cushion.
(c) The ballast bed has to be perfectly
level. Any variation in level may
affect the gauge adversely.
(d) Enough ballast shall be stacked along the
cess to enable the filling of ballast in the cribs on the same day.
(e) Longitudinal and cross drains may be
provided in turnout area to avoid accumulation of water.
(f) The site preparation to be completed well
before laying turnout ensuring deep screening of ballast in turnout length and
30m on either side along the track.
2.
Assembling :
(a) Ensure the availability of all fittings at
site strictly as per requirement of latest drawings for switch portion, lead
and crossing portion.
(b) The complete turnout will be assembled on
a level ground adjacend to the site of laying or on the loop line corrected to
turnout.
(c) Red/blue rounded marking on the sleepers
should invariably be kept on the right hand side irrespective of left hand or
right hand turnout.
(d) Spacing of sleepers should be strictly as
per layout drawing.
(e) The sleepers shall be perpendicular to the
straight track in switch portion only.
(f) In lead portion, the sleepers will be
inclined at half the angle between the normals to straight and curved track at
that point. Proposed disposition is
appended as Annexure-14/1.
(g) To ensure correct layout, laying of sleeper
falling at transition from switch to lead and lead to crossing portion should
be paid special attention. Sleepers in
the switch portion, lead portion and crossing portion are as under :-
|
Turnout |
Switch |
Lead |
Crossing |
|
1:8.5 |
1-13 |
14-41 |
42-54 |
|
1:12 |
1-20 |
21-64 |
65-83 |
(h) The spacing of the sleepers in the lead
portion should be as per layout drawing to make a radial or fan shaped
layout. The spacing has been worked out
separately for both the rails. This
separate spacing on two rails make the layout fan shaped in lead portion.
(i) The sleepers in the crossing portion
shall be perpendicular to bisecting line of crossing.
(j) Sleeper no. 3 & 4 may be placed for
housing motor with the extended portion of sleeper in reverse direction only in
circumstances where it cannot be avoided.
(k) The approach sleeper in advance of switch
portion should be provided without fail, they are for gradual elimination of
slope of rail top (1:20).
(l) The exit sleepers behind the crossing
portion should also be provided for gradual introduction of rail slope (1:20).
3. Insertion of pre-assembled turnout :
The
complete assembled turnout shall be inserted in position after breaking it into
three panels viz. Switch, lead and crossing portions by means of cranes or
rollers.
6. Manual
insertion : In case the PSC turnout sleepers are to be manually inserted,
then the same must be done sleeper by sleeper ensuring that at no time the
alignment and level is beyond permissible limits. This work may be done under a suitable speed restriction if
necessary and adequate mechanical means for packing the sleepers must also be
available.
ADVANCE
CORRECTION SLIP No. 61 Dated. 22.08.2000
(Bd's letter
No.97/CE-II/TS/2 Pt.2 dtd. 22.8.2000)
4. The para 248
(2) (a) and (b) be replaced with the following :-
(a) Broad Gauge :- The following minimum rail
sections are recommended based on the speeds obtainable and the traffic
condition :-
|
Traffic
density in GMT |
Routes |
||||||
|
A |
B |
C |
D.Spl |
D |
E.Spl |
E |
|
|
More
than 20 |
60 Kg |
60 Kg |
60 Kg |
60 Kg |
60 Kg |
60 Kg |
60 Kg |
|
60 Kg |
60 Kg |
60 Kg |
60 Kg |
60 Kg |
52 Kg/ 90 UTS |
|
52 Kg/ 90 UTS |
|
5-10 |
60 Kg |
52/90 |
52/90 |
52/90 |
52/90 |
52/90 |
52/90 |
|
Under
5 |
52/90 |
52/90 |
52/90 |
52/90 or 60 Kg (SH) |
52/90 or 60 Kg (SH) |
52/90 or 60 Kg (SH) |
52/90* (SH) or 60 Kg (SH) |
|
Loop line |
52 Kg (SH) |
||||||
|
Pvt. Siding |
52 Kg of T-18 quality or T-12 quality
second hand rails. |
||||||
Note : 52/90 represents 52 Kg/90 UTS
rail section.
(i) Existing
90R rails may be allowed to remain for speeds not exceeding 130 Km/h.
(ii)
On routes identified for running of 22.1 t axle load wagons, 60 Kg. rails shall
be used on all routes.
(iii) On
private sidings where BOX'N or 22.1 t axle load wagons ply, the rail section
should be 52 Kg. In case of operating
speeds exceeding 30 Km/h and going up to 50 Km/h, as also where BOX'N or 22.1 t
axle load wagons ply, T-12 quality rails should be used.
(iv) Head
hardened rails should be used for (a) local lines where EMU stock is running
(b) Ghat section with gradients steeper than 1 in 150 and/or curves sharper
than 2 degree (c) location where rate of wear of rails necessitates rail
renewal at frequency of 10 years or so.
These rails should be laid on continuous and long stretches.
(v) *
Second hand 52Kg rails may be used on case-to-case basis, with the prior
approval of Railway Board, depending upon quality of released rails available.
(b) Metre Gauge : The following rail sections
are recommended on MG routes :-
Route. Rail section recommended.
`Q' and `R1' 52 Kg (SH)/90R
(New)*
`R2' and `R3' 52 Kg (SH)/90R (SH)
`S' 52
Kg (SH)/90R (SH)/75R (SH)
* 90 R (New) to be only used with
specific approval of Railway Board, in case no suitable 52 Kg (SH) rails are
available for use on MG during renewal.
5.
The table `B' of para 305 (2) be deleted and the following sentence be added to
para 305 (2) :-
(iv)
All renewals on Metre gauge shall be with concrete, steel and CST-9 sleepers
(new or second hand)
ADVANCE
CORRECTION SLIP No. 60 Dated.
(Bd's letter
No.97/CE-II/TS/2/Pt.2)
The following sentence be added at the
end of existing para 237 (1) (l):-
In case of PSC sleeper layout with
elastic fastening, creep anchors need not be provided. In case excessive creep is observed at such
layouts, the condition of elastic fastenings may be examined and suitable
action be taken.
A new para-242 (3) (C) be added to read as under :-
Para 242 (3) (C) : The PSC sleepers
with elastic fastenings are considered as creep resistant and therefore no other
creep anchors are required. In case,
excessive creep is observed on PSC sleeper road, the condition of elastic
fastenings, sleepers and adequacy of ballast resistance should be examined. Action for replacement/renewal of fittings,
sleepers and providing adequateballast resistance etc. should be taken as
necessary.
ADVANCE
CORRECTION SLIP No. 59 Dated. 1.08.2000
(Board’s letter
No.2000/CE/ dtd. 1.8.2000)
Replace para 275(3)
with the following :
`(3)
Fixing of Guard rails : The ends of
guard rails should be bent vertically and buried and a block of timber fixed at
the end to prevent entanglement of hanging loose couplings. To ensure that guard rails are effective,
they should be spiked down systematically to every sleeper with two spikes
towards the centre of the track and one spike on the opposite site. Notching of the rail foot for spikes fixing
the guard rails should be done on every alternative sleeper. Sleepers
should be tied at both ends by MS Flats/tie bars fixed through holding down bolts.'
Replace para 724 (1)
& (2) with the following :-
`(1)
Arrangements should be made to stock sufficient quantities of rails, sleepers,
materials for cribs, ballast, sand/quarry dust and boulders at suitable points
near vulnerable locations, so that the materials may be rushed to site as
required.
(2)
Before the onset of monsoon, specified number of wagons loaded with sand/quarry
dust, ballast and boulders should be kept at appropriate stations for quick
movement to vulnerable locations.'
Replace para 723(9)
with the following :
`(9)
The prescribed reserve stock of boulders, empty cement bags, wire netting and
sand/quarry dust should be kept at specified locations for rushing to site, in
case of emergency and should be made good, in case of deficiency.'
ADVANCE
CORRECTION SLIP No. 58 Dated. 1.08.2000
(Board’s letter
No.97/CE-II/TK/15 dtd. 1.8.2000)
Existing
para 167, 168, 169 and 170 may be modified to read as under :-
167. Selection and training of keyman :
The
selection of Gangman to perform the duties of a keyman is to be considered as a
step in his training as Mate. Keyman
trained in laying and maintenance of LWR/CWR on concrete sleeper and possessing
valid competency certificates issued by Zonal/Divisional Training center should
only be posted on LWR/CWR section.
168 (1) Keyman's daily
inspection :
The
keyman shall inspect by foot his entire beat once a day, both the tracks and
bridges, and return along the opposite rail to that taken on his outward
journey in case of single line. On
double line, keyman will carry out one round of inspection in morning hours by
going along up line and then returning along Down line or vice-versa. On the days of Gang holidays and rest, he
shall perform the usual duties and get one day's rest in the week as per the
roster duties in force. On rest days or
during absence or leave or sickness, a senior intelligent gangman should be
deputed in place of the regular keyman.
(2) Roster duty hours of keyman :
The
roster duty hours of keyman for winter months should be so adjusted as to
ensure one round of track inspection in early morning to enable detection of
any rail or weld fractures that might have occurred during the night or early
morning. DEN/Sr.DEN of the section
shall decide and notify the exact timings and the period of each section.
169. Equipment
of keyman :
The
keyman shall carry with him on his rounds two red flags, and green flag, ten
detonators, a flangeway gauge if required, for unmanned level crossings, a
keying and spiking hammer, a fish bolt spanner, and two fish bolts, spare
fittings and a rail closure of 30mm size.
For the work of greasing of elastic rail clips wherever applicable,
keyman shall carry a wire brush, emery paper, a duster and grease.
170. Duties
of Keyman :
1)
While walking over his length, he should look for defects, such as loose fish
bolts, SEJ fittings in switches and crossings, fittings on girder bridges and
open top culverts, broken or burnt sleepers, broken plates or tie bars, attend to
them as necessary. If he finds that
fittings are consistently working loose even after repeated attention, he
should report the matter to the Mate, PWM and Permanent Way Inspector. If the defects are serious, he should at
once inform the Mate of the gang protecting the line in the meantime, if
necessary, according to rules.
2) He
shall keep a special watch on the rails and welds marked for observation by the
USFD team.
3)
If he should notice any condition of danger, such as broken rail, broken weld
or wash away of ballast, theft of fittings in large numbers etc., he shall at
once protect the line as per rules, take such action as is possible and report
the matter to the Mate, the nearest Station Master and Permanent Way Inspector.
4)
At unmanned level crossings, he shall maintain the flange ways between the
check and the running rails clear of obstructions.
5) In track
other than with elastic fastenings, the keyman in addition to his normal round
of the whole beat and inspection and tightening of loose fittings, should
attend one telegraph post (TP) on one line thoroughly on every day. This thorough attention should consist of
tightening of each bolt and fittings in these TPs of the beat during that
particular day. Missing keys and other
missing fittings will be recouped by him.
He shall also ensure correct driving of fittings in this stretch.
6) Where
the beat of a Keyman consists of PRC sleepers, apart from his round of the
beat, the keyman should also carry out in a systematic manner from one end
greasing of the ERC and eyes of inserts at the rate of 15 sleepers per
day. Greasing shall be done as per the
procedures laid down in para 1411(5) (b) of IRPWM tackling one clip at a time.
7)
Keyman with the assistance of one gangman will also carry out rail end
examination, lubrication of fish plated joints as per direction of PWI/PWM.
8)
For imposing of caution after stopping the train or otherwise wherever required
for safety, Keyman will be provided cyclostyled slips by PWI. Keyman after filling location and speed will
hand over the same to Driver or ASM and obtain acknowledgement.
9)
The following are the special duties and responsibilities of the keyman in
LWR/CWR territories :-
(i) Periodical
(fortnightly) oiling and greasing of SEJ, checking and retightening of
fastenings at SEJ and other sleepers, if necessary (para 6.2.6 of LWR Manual).
(ii) Replacement
of missing fastenings not requiring lifting or slewing of track as per para
6.2.6 (I) of LWR Manual.
(iii) To
ensure that all creep anchors where provided butt against the sleepers and in
case of large scale displacement of anchors, he shall report the matter to
Mate/PWM/PWI (Subsection)/PWI (incharge).
(iv) To
watch for sun kinks, loose or missing fastening which may result in buckling or
any damage to LWR/CWR and SEJ. On
noticing any buckling or damage to track, he shall take necessary action to
protect the track and report the same immediately to PWI (Sub-section)/
PWI(incharge), Station Master. However,
he will continue to perform his Keyman's duties of daily inspection.
(v) To
keep a sharp look out in cold mornings, especially during winters to detect any
fractures which may occure, in case of rail/weld fracture, he shall take prompt
action to protect the track and carry out emergency repairs to permit the
restoration of traffic promptly and report to PWI (Subsection)/
PWI(Incharge)/nearest Station Master (para 7.2.2 and 7.2.3 LWR Manual).
10. The
Kayman shall promptly report to Mate/PWI any encroachment or unauthorised
structures as and when they take place in the Railway land in his beat.
11. After
completing inspection of the beat, the Keyman should assist the Mate in the
day's work being done.
12. When
materials, such as dynamo-belts, engine tools and personal articles of
passengers, are found on line, the Keyman should collect them and arrange for
handing them over to the nearest Station Master.
13. The
Keyman will remain incharge of the gang in absence of the Mate once a
week. On that day, the Mate is required
to carry out the work and duties of Keyman.
14. Whenever
directed he will supervise rail dolly working.
However, he must have competency certificate for the same.
An additional para
may be added as under :-
168. Keyman's book :
(i) Printed
keyman's book should be supplied to every keyman.
ii) The
keyman shall maintain the book upto date wherein all special work done, missing
fittings and their recoupment with location and date are to be entered.
(iii) PWI
should make a date wise schedule and enclose with the Keyman's book the Kms/TPs
that the Keyman has to attend on each day of the month to complete the task
required to be done as per sub para 6, 7, 9(I) of para 170 above. PWIs and AENs during their inspections
should check to ensure that such Kms have really been thoroughly attended to
and initial against the entries.
(iv) Special
locations to be watched by the keyman should be entered in the book.
v)
The special fittings like joggled fish plates and other material provided in
the section which are vital for safety and for restoration of traffic should
also be mentioned in the book.
ADVANCE
CORRECTION SLIP No. 57 Dated. 17.02.2000
(Board’s letter
No.98/CE-II/TS/1 Pt. Dtd. 25.7.2000)
The following may be added to para 202
(1) under Group`B' route:
(XVII) - Chennai
beach - Dindigul.
(XVIII) - Bangalore-Dharmavaram-Gooty.
ADVANCE
CORRECTION SLIP No. 56 Dated. 13.07.2000
(Board’s letter
No.Track/21/99/0907/7 dtd. 13.7.2000)
Para 252 (3) of Indian Railway's
Permanent Way Manual, 1986 Edition may be modified as follows :-
252 (3) `Ultrasonic Rail Flaw
Detection - Ultrasonic testing of rails is a specialised activity and the
inspectors carrying out the ultrasonic testing of rails shall be trained by
RDSO, in the techniques of USFD testing.
Each zonal railway shall create adequate number of ex-cadre posts of
inspectors to ensure that entire track length in their jurisdiction is
ultrasonically tested at the laid down periodicity.'
(a)
Description of instrument - Manually operated….
ADVANCE
CORRECTION SLIP No. 55 Dated. 31.05.2000
(Board’s letter
No.98/CE-II/CS/2 dtd. 31.5.2000)
The following changes may be made in
paras 910 & 1007 of IRPWM :-
Para
910 (1) (v) be modified to read as under :- Gatemen working on double
line/multiple lines, ghats, suburban and automatic block territories shall be
provided with three fusees. Gatemen
working on single line sections shall be supplied with one fusee.
The note to para 910 be modified to read as under :-
Note : In the case of level
crossings in multiple lines and hand signal flags/lamps, detonators shall be
increased suitably.
Para
1007 (1) (1) be amended to read as under :- Three flare signals (fusees) on
double/multiple lines, ghats, suburban and automatic block territories and one
fusee on single line sections.
ADVANCE
CORRECTION SLIP No. 54 Dated. 29.05.2000
(Board’s letter
No.99/CE-II/TK/20 dtd. 29.5.2000)
The existing para 277 be substituted
with the following :-
1.
On the bridge approaches, for a length of 100m, PSC sleepers with arrangement
for fixing guard rail (Drg.No.RDSO/T-4088 to 4097) should be provided
irrespective of the type of sleepers in the track.
2.
The full compliment of track fittings at bridge approaches upto 100 metres must
be ensured at all times to maintain required track geometry. Any deficiency noticed must be recouped
immediately.
3.
The rail level of track in approaches of bridge should be maintained as per
L-section and dips in rail level immediately after abutments must be
avoided. The alignment and super
elevation in case of curved track should also be maintained as per design. Rail joints should be avoided within three
metres of a bridge abutment.
4.
Full ballast cushion as specified for LWR track should be provided upto 100
metres from the abutment.
5.
On the bridge approaches, for a length of about 100 metres, width of cess
should be 90 cm. Clear of full ballast section to maintain ballast
profile. Ballast retaining wall should
also be provided for a length of one rail from the abutments to maintain
ballast section. The condition of the
ballast wall should be checked and repairs carried out whenever necessary.
6.
Switch expansion joints should be provided at the bridge approaches in LWR/CWR
track as per provisions of LWR manual.
ADVANCE
CORRECTION SLIP No. 53 Dated.
(Board's letter
No.88/Track-III/TK-18/Vol.III (Part)).
The
existing para 203 (1) be replaced to read as under :-
(1) System
to be adopted – The track should be maintained either by conventional
system of track maintenance or by 3-tier system of track mainteannce.
The existing para 205 be renumbered as
Para 205 Maintenance Planning – (1).
New
para 205 (2) be included to read as under :-
(2) For sections nominated for mechanised
maintenance, annual plan for deployment of various track machines shall be
finalised by CTE(MC)/CTE of the Zonal Railway and he shall arrange to deploy
the machines accordingly.
The
existing para 225 regarding `Maintenance by Measured shovel packing is deleted.
The
existing para 228 be replaced to read as under :-
228. 3-tier
system of track maintenance: - (1) 3-tier System of track maintenance shall
be adopted on sections nominated for mechanised maintenance. This shall consist of the following 3 tiers
of track maintenance:
(i)
On-track machines (OMU)
(ii)
Mobile Maintenance Units (MMU)
(iii)
Sectional Gangs
(2) Large track machines for track maintenance
include Tie-tamping machines for plain track and points and crossings, shoulder
ballast cleaning machines, ballast-cleaning machines, ballast regulating
machines and dynamic track stabilizers.
These machines shall be used as per the various instructions issued in
Indian Railways Track Machines Manual.
These machines shall be deployed to carry out the following jobs:
(a) Systematic
tamping of plain track as well as Points & Crossings;
(b) Intermediate
tamping of plain track as well as Points & crossings;
(c) Shoulder
ballast cleaning;
(d) Ballast
profiling/redistribution;
(e) Track
stabilization;
(f) Periodical
deep screening.
(1) Mobile Maintenance Units :
(a) The
mobile maintenance units (MMU) shall consist of two groups:
(i) MMU-I
: One for each PWI’s section.
(ii) MMU-II:
One for each sub-division
(b) The
functions of MMU shall be as below :
MMU-I, (Rail-cum-Road Vehicle based)
one with each PWI incharge with a jurisdiction of 40 – 50 Kms. double line or
90-100 Kms. single line:
(i) Need
based spot tamping;
(ii) In-SITU
rail welding
(iii) Casual
Renewal and repairs except planned renewals
(iv) Overhauling
of Level Xings
(v) Replacement
of glued joints
(vi) Rail
cutting/drilling and chamfering
(vii) Permanent
repairs to fractures
(viii) Creep
or gap adjustments involving use of machines
(ix) Distressing
of LWR/CWR
(x) Loading/Unloading
of materials
(xi) Any
other functions assigned.
MMU-II
: (Road Vehicle Based ) : one with each sub division :
(i) Reconditioning
of Turnouts
(ii) Minor
repairs to the equipments of MMU
(c) The MMU shall be equipped with the
following equipments. These equipments
shall be used according to the working instructions, as and when issued.
List
of equipments for MMU-I :
A.
Communication Equipment
1. Walkie
Talkie | 4 sets
2. Portable field telephones |
B.
Rail Cutting/Drilling Equipment
3. Disc
Cutter 1
4. Rail Cutting Machine 1
5. Rail Drilling Machine 1
6. Chamfering kit 1
C.
Rail Welding Equipment
7. Rail
Welding Equipment 2 sets
8. Weld Trimmer 1
set
9. Rail Profile Grinder for welded joints 1 set
D.
Spot Tamping with Lifting Lining
10.
Off Track Hand Held Tamper
With Generators 1 set
11. Lifting Jack-hydraulic/mechanical 4 sets
12. Lifting-cum-Slewing Device 2
sets
E.
Destressing Equipment
13. Rail
Tensors-Hydraulic/mechanical 2 sets
14. Rollers, wooden mallets 1
complete
set
for
Distressing
3
Km. LWR
F.
Inspection Gadgets
15. Inspection
Kit 1 No.
16. Gauge cum Level 1
No.
17. Rail Thermometer 1
No.
18. Vernier Calipers 1
No.
19. Micrometer 1
No.
G.
Material Handling Equipment
20. Rail
Dolly 6
No.
21. Mono Rail Wheel Borrow 2
No.
H.
Safety and Protection Equipments
22.
Warning System
23.
Red Banner Flag
24.
Red Hand Signal Flag
25.
Green and Signals
26.
Detonators
I.
Gas Cutting Equipments with Accessories : 1 set.
List
of Equipments for MMU-2 :
A.
Points and Crossing Recording Equipment :
1. Welding
Generator 1 set
2. Arc Welding Equipment 1
set
3. Hand Held Rail Grinder 2
sets
B. For
Minor Repairs to Equipments :
4. Spanner of sizes 2
sets
5. Trifer 2
6. Files of Sorts 2
sets
7. Bench Drill 2
8. Vice Bench 2
9. Bench Grinder 2
(4) Sectional
Gangs :
The sectional gangs, under 3-tier system of track maintenance
shall perform the following functions :
(a) Patrolling
of track :
(i) Keyman’s
daily patrol
(ii) Hot/cold
weather patrolling
(iii) Monsoon
Patrolling
(b) Watching
vulnerable locations
(c) Attention
of emergencies viz. temporary repairs of fractures.
(d) Need-based
attention to bridges, turnouts, SEJs and approaches of level crossings.
(e) Greasing
of ERCs, lubrication of joints, casual changing of rubber pads and other
fittings
(f) Minor
cess repairs
(g) Cleaning
of drains and boxing of ballast
(h) Attention
to loops
(i) Creep
and gap adjustment not involving use of machines
(j) Cleaning
of crib ballast for effective cross-drainage
(k) Pre
& post tamping attention
(l) Assistance
to MMU & OMU as required
(m) Any
other functions assigned.
ADVANCE
CORRECTION SLIP No. 52 Dated. 24.04.2000
(Board's letter
No.98/CE-II/TS/4 dtd. 24.4.2000).
The existing legend of the annexure
2/4 of para-211 of IRPWM be modified as under :-
|
Rail
Section/UTS |
Colour |
Indigenous |
Imported |
|
|
Yellow |
|
|
|
|
Yellow |
|
|
|
|
Green |
|
|
|
|
Green |
|
|
|
|
Red |
|
|
|
|
Red |
|
|
|
|
Sky
Blue |
|
|
|
|
Sky
Blue |
|
|
|
|
Blank |
|
|
|
|
Blank |
|
|
|
|
To
be decided by Rly. |
|
|
|
SLEEPERS |
|||
|
Green |
|
|
|
Green |
|
|
|
Yellow |
|
|
|
Red |
|
|
|
Black |
|
|
ADVANCE
CORRECTION SLIP No. 51 Dated. 21.04.2000
(Board's letter
No.98/CE-II/CS/2 dtd. 21.4.2000).
A new para 251 (5) may be added to
IRPWM,1986 to read as under:
Para
251(5) Chamfering of bolt holes in rails : (a) General : (i) Chamfering of
bolt holes work hardens the periphery of holes and thereby delays the formation
of star cracks. The chamfering of hole
takes 5 minutes per hole. Each drilled
hole shall be chamfered.
(ii) Existing hold holes in fracture prone
zones should be chamfered if not elongated.
In case of elongated holes, the chamfering bit will not be in contact
with the full edge of the bolt holes and there will be uneven hardening of the
metal resulting in stress concentration in weaker-zones. Therefore, such portion of rail should be
removed; holes should be drilled and chamfered.
(b) Equipment
for chamfering of bolt holes : Work hardening of bolt holes should be done
with chamfering kit of approved make.
The chamfering kit consists of the following :
Equipment
(as per Fig.1)
Qty.
(i) High tensile bolt M-20 1
No.
(ii) High tensile nut for M-20 bolt 1 No.
(iii) Sets of 2 H.S.S. chamfering bits 1 set
(iv) 19mm sq. drive sockets size 32mm 8 Nos.
(v) Set of 2 packing pieces (sleeves) 1 set
(vi) T-400
torque-wrench with built-in rachet
Mechanism
1.25m length 1 No.
(c) (i) Chamfering
of bolt holes in the welded rail panels should be done before despatch in the
Flash Butt Welding Plants, if situation so warrants.
(ii) When rails in track are end-cropped, new bolt holes should
be chamfered at site.
(iii) Bolt holes in new rails received directly
from steel plant should be chamfered before rails are laid in track.
(d)
Procedure for chamfering of bolt holes :
(i) The nut of high tensile steel bolt is
removed and one packing piece is inserted in the shank followed by one side of
the H.S.S. chamfering bit.
(ii) The high tensile steel bolt is inserted
with 2 pieces in the rail hole.
(iii)
On the other face of the rail hole, the second half of the HSS chamfering bit
is inserted over the shank followed by the second packing piece.
(iv)
The nut on the high tensile steel bolt is replaced.
(v)
Pre-set torque-wrench on nut at torque value of 52 Kg-m equivalent to an exile
force of 12.5 tonnes, is applied. The
nut is tightened with the torque wrench.
As soon as the present torque is attained, the torque wrench will
automatically trip indicating complete tightening to pre-set torque valve.
(vi)
The nut by reversing the torque wrench is unscrewed and HTS bolt is
removed. The process is repeated on
other rail holes.
(e) Chamfering of each hole should be done
under the supervision of Mate/Keyman.
ADVANCE
CORRECTION SLIP No. 50 Dated. 14.04.2000
(Board's letter
No.99/CE-I/LX/80 dtd. 14.4.2000).
The existing para 918 of IRPWM be
replaced with the following :-
Para
918 - Provision of speed breakers on the approaches of level crossing :-
Provision of rumble strips on approaches of level crossings as per the standard
design is the responsibility of Road authorities. Matter may be persued with all State Governments/Road authorities
to ensure that rumble strips are provided on all level crossings as per
standard design over the total width of the road i.e. edge of the berm to edge
of berm with proper road warning signs as per the standard design. However, it is incumbent upon Railways to
provide speed breakers as per the standard design on both manned as well as
unmanned level crossing irrespective of whether the approach road are metalled
or un-metalled, as a temporary safety measure, till such time these are
replaced with rumble strips of proper design by the Road authorities. While providing speed breakers, following
guidelines may be observed :-
(2)
One speed breaker should be provided on either approach of level crossings
located within the Railway land boundary at a distance maximum feasible but not
exceeding 20m covering full width of the road including berms as per Annexure -
9/6. For safety reasons, the paint
marking should be provided and their maintenance ensured.
(3)
Standard warning signs for speed breakers as per Annexure - 9/7 should be
invariably provided at a prescribed distance as indicated in item 19 of
Annexure 9/1 to para 904.
(4)
Speed breakers should be constructed with hot pre-mix bituminous material, well
compacted after laying on well prepared surface. Enough time is to be allowed for the bituminous material to
harden before opening it to the traffic.
On berms and unmetalled roads, the speed breakers should be supported on
proper base of compacted road metal.
Annexure
- 9/6
Annexure
- 9/7
ADVANCE
CORRECTION SLIP No. 49 Dated. 11.04.2000
(Board's letter
No.97/CE-II/Misc/5 (CS)/Pt. Dtd. 11.4.2000).
The following changes may be made in
the para - 263 of IRPWM :-
In Annexure 2/11, 2/12, 2/13 and 2/14
to para 263 the following changes may be made :-
Annexure
2/11 : Under column F the figure of
6100 be replaced with 6850.
Under
column F1 the figure of 5490 be replaced with 6250.
Annexure
2/12 : Under column F the figure of
4880 be replaced with 5850.
Under column F1 the figure of 4270 be replaced
with 5250.
Annexure
2/13 : In the diagram the top width of
6100mm be replaced with 6850mm.
Annexure
2/14 : In the diagram the top width of
track shown as 4880mm be Replaced with 5850mm.
ADVANCE
CORRECTION SLIP No. 48 Dated. 11.04.2000
(Board's letter
No.93/CE-II/PRA/40 dtd. 11.4.2000)
The existing para 1208 of IRPWM be
replaced with the following :-
1208
: Official-in-charge of Material Train :-
Whenever a material train is worked it shall be accompanied by a Guard. As the Guard is not qualified to carry out
such duties as working of hoppers, distribution of ballast/materials,
supervising loading and unloading, maintaining muster rolls and daily reports
of labour and preparation of daily reports on material train working a
qualified engineering official should be deputed on the train to ensure working
of material train to the programme specified by Assistant Engineer.
ADVANCE
CORRECTION SLIP No. 47 Dated. 15.03.2000
(Board's letter
No.99/CE-II/PRA/Accd./1 dtd. 15.3.2000))
The existing para 243 (4) be replaced
with the following para :-
234
(4) Action on buckling of track : If a buckling does occur or appears
imminent, the track should be protected immediately with hand signal flags and
detonators as per the protection rules laid down. The buckled rails shall preferably be cut adequately apart not
less than 6.5 metres. The track shall
then be slewed to the correct alignment and cut rails of the required length
shall be inserted to close the gaps making due provision for welding of joints
on both rails. The cut rails shall then
be connected by use of special fish plates and screw clamps and the line opened
to traffic with speed restriction. It
may not be possible to do any more until the temperature drops when the joints
must be adjusted. Particular care must
be taken to see that the factors which contributed to the buckling i.e. jammed
joints, seized fish plates or shortage of ballast receive appropriate attention
without delay.
ADVANCE
CORRECTION SLIP No. 45 Dated. 17.02.2000
(Bd's letter
No.94/Track-III/TK/23-Vol.II dtd. 17.2.2000)
The para 607 of IRPWM 1986 may be read
as under :-
Para
607 may be read as 607 (1).
A
new Para 607(2) may be added to read as under :-
The following limits of track
tolerances are prescribed for the guidance of the Engineering officials on the
suitability* of standard of maintenance of track for sanctioned speeds above
100 Km/hr. and upto 140 km/hr on BG track.
(i)
Alighment defects (versine measured on a chord of 7.5 metres under floating
conditions)
a)
On Straight Track : 5mm; values upto 10mm could be tolerated at few
isolated locations.**.
b)
On Curves : 65mm over the average
versine, Values up to 6
7mm could be tolerated at few isolated locations**.
Total
change of versine from chord to chord should not exceed 10mm.
(ii) Cross Level Defects :- No special
tolerance limits. As regards cross levels, the track should be maintained, to
standards generally superior to that at present available on main line track on
which unrestricted speeds upto 100 Km/hr. are permitted.
(iii) Twist (to be measured on a base of 3.5 m)
(a)
On straight and curve track, other than on transitions - 2mm/metre except that
at isolated locations**, this may go upto 3.5mm/metre.
(b)
On transitions of cruves - Local defects should not exceed 1mm/metres, except
that at isolated locations** this may go upto 2.1 mm per metre.
(iv) Unevenness rail joint depressions (versine
measured on a chord of 3.5m) - 10mm in general and 15mm for isolated
locations**.
(v) Gauge variations - No special
specifications. The maximum limits for
tight and slack gauge should be as indicated in Para 224(2)(e).
(*) Suitability - Suitability refers to good
riding quality for passenger comfort and not from stability point of view.
(**) In above `few isolated locations' has been
taken is not exceeding 10 per km.
ADVANCE
CORRECTION SLIP No. 42 Dated. 05.11.1999
(Bd's
lr.No.98/CE-II/CS/2 dtd. 5.11.99)
The following may be added to para 301
of IRPWM.
(8)
Through Turnout Renewal (TTR)
(9)
Through Fitting Renewal (TFR)
(10)
Through Weld Renewal (TWR)
(11)
Through Bridge Timber Renewal (TBTR)
Para 1411 (4)
may be modified to read as under :-
The
existing matter be numbered as 4 (a).
Para 1141 (4) (b)
be added to read as under :-
(b) Periodicity of Measurement of Performance of Elastic Fastening Components.
1. SAMPLES,
SIZE AND TESTING FREQUENCY : (i) SAMPLE SIZE : Toe load of elastic rail
clip should be measured on 1% of ERCs randomly on every 100 sleepers (all 4
ERCs to be measured on one sleeper).
(ii) TESTING
FREQUENCY : Initial testing of ERCs is to be done after four years of
passage of 200 GMT of traffic, whichever is earlier. In corrosion prone area, the initial testing of ERC is to be done
after two years or passage of 100 GMT, whichever is earlier.
(iii) Subsequent testing will be done every four
years or 200 GMT in normal areas and two years or 100 GMT in corrosion prone
areas, whichever is earlier. However, if
20% or more of sample size records toe load below 600 Kg. both frequency of
inspection and sample size are to be doubled.
2. REPLACEMENT
OF ERC : (i) If 20% or more of sample size records toe load below 400 Kg
which is to be confirmed by 5% sample size, proposal of through fastening
renewal should be initiated.
(ii) The provisions given above are only for
guidance of Railways. The Railways on
the basis of the overall condition of track, pattern of traffic and the
required level of maintenance should undertake the large-scale replacement of
the fastening.
(iii) Further, as the loss of toe load is
reflective of conditions of other elastic fastening components like groove
rubber sole plate, GFN/metal liners etc. as well, the railways may also record
condition of these components along with measuring toe loads for elastic rail
clips.
ADVANCE
CORRECTION SLIP No. 41 Dated. 02.11.1999
The existing para 302 (a) to be
replaced with the following :-
(a) Incidence
of rail fracturesfailures : A spate of rail fractures on a particular
sections having 5 withdrawals of rails per 10 Km. in a year due to fracture
and/or rail flaws detected ultrasonically falling in the category of IMR &
REM will have priority while deciding rail renewals. In case the rail failures at fish plated/welded joints are
predominant, end cropping with or without welding could be considered.
ADVANCE
CORRECTION SLIP No. 40 Dated. 27.09.1999
The para 913, 3(a) & (b) of the
IRPWM 1986 together with Annexure 9/3 to para 913 be replaced with the
following :-
(a) On double line, if both lines are
obstructed during day, he shall plant a red banner at a distance of 5 metres on
the line on which a train is expected to arrive first, then plant another red
banner flag on the other line at the site of obstruction. He shall then pick up red hand signal and
showing it, proceed on that line towards the direction of an approaching train
to a point 600 metres on Broad Gauge and 400 metres on Metre Gauge and Narrow
Gauge from the level crossing and place one detonator on the line, after which
proceed further to not less than 1200 metres from the level crossing on Broad
Gauge and 800 metres on Metre Gauge and Narrow Gauge and place 3 detonators on
the line about 10 metres apart. Having
thus protected the line on which a train is expected to approach first, he
should return to the level crossing, picking up the intermediate detonators on
his way back. He shall then proceed on
the other line showing red hand signal, place detonators similarly and return
to the site of obstruction to warn the Driver of an approaching train.
Provided
that on those Metre Gauge sections where trains run at more than 75 Km/h, the
detonators shall be placed at distance to be specified under special
instructions by the Administration (Annexure 9/3).
(b) On single line, if the line is obstructed
during day, he shall plant a red banner flag towards the direction from which a
train is expected to arrive first, then plant another banner flag towards the
opposite direction at the site of obstruction.
He shall then pick up red hand signal and as in sub-para (a) above,
protect the line in the direction from which a train is expected to approach
first, return to the site of obstruction, and proceed with all haste in the other
direction to protect the line. Having
protected the line on both sides, he should station himself at the place of
obstruction to warn the Driver of an approaching train (Annexure 9/3).
ADVANCE
CORRECTION SLIP No. 39 Dated. nil
The table at para
244(4)(a) be substituted with the following
:-
|
Traffic Density in GMT |
Routes |
||||||||||||
|
A |
B |
C |
D-Spl |
D |
E-Spl |
E |
|||||||
|
Number of sleepers per km. |
|||||||||||||
|
More than 20 |
1660 |
1660 |
1660 |
1660 |
1660 |
1660 |
1660 |
||||||
|
10-20 |
1660 |
1660 |
1660 |
1660 |
1540 |
1660 |
1540 |
||||||
|
Under 10 |
1660 |
1540 |
1540 |
1540 |
1540 |
1540 |
1540 |
||||||
|
Loop lines |
1340 |
1340 |
1340 |
1340 |
1340 |
1340 |
1340 |
||||||
|
Pvt. siding |
1340 |
1340 |
1340 |
1340 |
1340 |
1340 |
1340 |
||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(i) For routes identified for running 22 t
axle load wagons, Sleeper density of 1660 nos/km should be maintained.
The Table (A) of
para 305 (2) be substituted with the following
:-
(i)
All primary renewals in future shall be carried out with 60 Kg. PRC sleepers.
(ii)
PRC or ST sleepers may be used on loop lines and private sidings.
(iii)
ST sleepers used on loop lines and private sidings may be with elastic or rigid
fastenings.
The para 248(2) (a)
be replaced with the following :-
The
following minimum rail sections are recommended based on the speeds obtainable
and the traffic condition :-
|
Traffic
Density in GMT |
Routes |
||||||
|
A |
B |
C |
-Spl |
D |
E-Spl |
E |
|
|
More
than 20 |
60 Kg |
60 Kg |
60 Kg |
60 Kg |
60 Kg |
60 Kg |
60 Kg |
|
10-20 |
60 Kg |
60 Kg |
60 Kg |
60 Kg |
52/90 |
60 Kg |
52/90 |
|
5-10 |
60 Kg |
52/90 |
52/90 |
52/90 |
52/90 |
52/90 |
52/90 |
|
Under
5 |
52/90 |
52/90 |
52/90 |
52/90 or 60 Kg (SH) |
52/90 or 60 Kg (SH) |
52/90 or 60 Kg (SH) |
52/90 or 60 Kg (SH) |
|
Loop Lines |
52 Kg (SH) |
||||||
|
Pvt. Siding |
52 Kg. or T-18 quality or T-12
quality second hand rails. |
||||||
(i)
Existing 90R rails may be allowed to remain for speeds not exceeding 130 Km/h.
(ii) On
routes identified for running of 22 t axle load wagons, 60 Kg. rails shall be
used on all routes.
(iii)
On private sidings where BOX'N or 22 t axle load wagons ply, the rail section
should be 52 Kg. In case of operating
speeds exceeding 30 Km/h and going up to 50 Km/h, as also where BOX'N or 22 to
axle load wagons ply, T-12 quality rails should be used.
(iv) Head
hardened rails should be used for (a) local lines where EMU stock is running
(b) Ghat section with gradients steeper than 1 in 150 and/or curves sharper
than 2 degree (c) location where rate of wear of rails necessitates rail
renewal at frequency of 10 years or so.
These rails should be laid on continuous and long stretches.
ADVANCE
CORRECTION SLIP No. 38 Dated. 08.09.1999
(Bd's
lr No.Track-21/99/0907/7 dtd. 8.9.99)
Para 281(c) of IRPWM 1986 may be
modified as under :-
The
instructions for Fabrication, installation and Maintenance of Glued insulated
rail joings as given in the `Manual for
Glued Insulated Rail joints, 1998' issued by RDSO, should be strictly
followed.
ADVANCE
CORRECTION SLIP No. 37 Dated. 01.09.1999
(Bd's
lr No.98/CE-II/CS/2 dtd. 1.9.99).
Existing
Note (I) at the end of para 807 (2) (b) shall be modified as under:-
Note
(I) : Annexure 8/3 and 8/3A indicate the distance at which these are to be
fixed.
The
following new sub-para 2 (a) along with Annexure 8/3 is to be added to para 808
:-
2(a) Multi Speed Restriction (i.e. existence of
two or more than two speed restrictions in continuation) : When work of deep
screening or sleeper renewal is in progress, there is situation of having two
or more than two speed restrictions in continuation. In such situation, placement of speed boards for following speed
restriction shall be as under :-
(i) In case of following speed restriction
being more restriction, a minimum of 200m track should be under earlier speed
restriction zone. If not, then only one
SR board should be provided, considering that the previous speed restriction is
at par with the following SR, which is more restrictive.
(ii) In case of following speed restriction
being less restrictive, corresponding speed indicator board for following speed
restriction shall be placed at a distance equal to the length of the longest
goods train operating on the section after termination point of previous speed
restriction zone.
Existing
sub-para 2 or para 808 shall be renumbered as 2(b) and modified as under :-
2(b) The details and position of fixing each
indicator are detailed in Annexure-8/4, 8/3 and 8/3A.
ADVANCE
CORRECTION SLIP No. 36 Dated. 24.08.1999
The para 503 of IRPWM 1986 may be
replaced with the following:
Alumino
thermic Welding of rails :
Alumino Thermic Welding of rails may
be carried out in accordance with the detailed procedure laid down in the
Manual for Fusion Welding of Rails by Alumino Thermit Process, September
1996. A thermit weld done in situ shall
be joggle fish plated with four clamps and supported on wooden blocks till
tested as good by USFD.
The
following may be added as para 127(3) :
Quality of welding
and avoidable fractures :
The direct responsibility for quality
of AT welding being done in the section shall rest on the PWI incharge of the
section. Responsibility for avoidable
fractures taking place in the section shall also rest with the PWI incharge of
the section, except in cases where the USFD testing was done and found good
upto three months before the fractures.
ADVANCE
CORRECTION SLIP No. 35 Dated. 19.08.1999
(Bd's
Lr.No.99/CE-I/LX/80 dtd. 19.9.99)
The existing para 901 of Chapter IX of
IRPWM, 1996 be modified to read as follows :-
901 General
Location : As far as
possible, new level crossing should not be located in Marshalling yards/Station
yards within Station limits from safety and operational considerations. Efforts should be made to shift the existing
level crossings, which are within station limits to the locations outside
station limits. During planning of
gauge conversions, yard remodelling and doublings, the planning of the yard
should be such that in case any manned level crossing falls within the station
limit, its operation from the cabin should be possible and this should form
part of the main work.
The existing part 910(4)(c) of chapter
IX of IRPWM -1986 be modified to read as under :-
910(4)(c)
: "Height Gauges should be located
at a minimum distance of 8 metre from gate posts. In exceptional circumstances where site condition do not
permit. Chief Engineer can give exemption
in these standards subject to a minimum of 8 metre distance from the centre
line of the track. Road surface upto
this point may be at the same level as
the road surface inside the gate posts."
The
existing sub para 919(2) and 919(5) of IRPWM - 1986 should be deleted.
Sub
item (iii) under Column (5) and (6) of item No.9(a) of Annexure-9/1 of IRPWM -
1986 should be deleted.
The
new para no.924 may be added to chapter IX of IRPWM - 1986 to read as under :-
924. Provision
of New Level Crossings/Manning/Demanning/Elimination:-
(a) Provision of the new level crossings
: If, provision of new level crossing is inescapable, then only manned level
crossing is to be provided. This is applicable to all existing lines, new
constructions and gauge conversions. However, these instructions are not
applicable in case of private sidings.
(b) Manning of Unmanned Level Crossing :
(i) Based
on traffic density, visibility and regular plying of buses etc., unmanned level
crossings have been categorised into I-V categorised for manning at Railway's
cost in a phased manner on a programmed basis as per following priority.
Category-I :Level Crossings where the Train Vehicle
Units
(TVUs) exceed 10000.
Category-II :Level Crossings where TVUs exceed 6000
and
where visibility is
restricted.
Category-III : Level Crossings where TVUs is less than
6000 and
visibility is restricted but
buses, motor vehicles
do not ply regularly.
Category-IV : Level
Crossings where TVU is less than 6000 and
visibility is restricted but
motor vehicles
do not ply.
Category-V : Level
crossings where visibility is adequate but
traffic density exceeds 6000
TVUs.
(ii) All unmanned level crossings on Rajdhani
and Shatabdi routes where maximum permissible speed is 120 Kmph or more should
be manned on priority.
(iii) For manning of unmanned level crossings
with traffic density more than 10000 TVUs, Board's approval is not
required. However, in all other cases
Board's sanction is required.
(c) De-Manning/Elimination
of the Level Crossing : The existing manned level crossings should not be
demanned. However, the detailed
review/survey of the existing level crossings both manned and unmanned to be
carried out with a view to eliminate them by either passing the road through an
existing bridge or by constructing link roads to combine two or more level
crossings etc.
A new para no.925 may be added to
chapter IX of IRPWM - 1986 to read as under :-
925. Criteria for replacement of existing level
crossings (other than those provided on `deposit terms') with Road Over/Under
Bridges on cost sharing basis :
(1) Minimum Train Vehicle Units on a Level
Crossing should be 1 lakh per day to become eligible for replacement with Road
Over/Under Bridges on `Cost Sharing' basis.
However, this could be relaxed in the following cases :-
(a)
Suburban sections having high frequency of train services; and
(b)
Near stations where detentions to road traffic are very high on account of
either shunting operations or multi-directional recepit/despatch of trains or
stabling of trains etc.
(2) Preference should be given to the Level
Crossings located on trunk routes vis-ŕ-vis those located on branch lines. In any case, minimum number of times the
level crossing is required to be closed against the road traffic should atleast
be 12 times per day.
(3) Subject to (1) and (2) above, priority
should generally be accorded by the concerned State Government giving
preference to Level crossings on National Highways.
(4) In case of Road Over/Under Bridges
constructed in replacement of busy level crossings situated in
Municipal/Corporation/Metropolitan areas where Light Vehicular traffic is
considerable and where the Railways are satisfied that closure of the level
crossings would cause hardship, additional provision may be made for
construction of the sub-way or a light Over Bridge with ramps for the use of
light vehicular traffic at the time of framing the proposal for the
construction of Road Over/Under Bridges.
The proposals for providing the ramps/sub-way should be examined
critically and should be provided for only in the case of genuine hardships and
not as a matter of course. The cost of
these ramps/subway will be shared equally with the Sponsoring Authority on
50:50 basis.
(5) Closure of the Level Crossings should be
ensured before commissioning of the Road Over/Under Bridges. All such cases where State/Local Authorities
do not agree to abide by this should be reported to the Railway Board promptly.
ADVANCE
CORRECTION SLIP No. 34 Dated. 06.08.1999
In continuation of par 252(3) of
Indian Railway Permanent Way Manual, 1986, part 252(4) may be added as follows
:
252(4) USFD
Testing of Service Rails :
No rail untested by USFD shall be laid
in the track whether for new lines or layouts or renewals or for repair works
or even temporarily such as service rails for PQRS work. For repairs and casual
renewals, a location-wise imprest of tested rails of various lengths (13m, 9m,
6m) shall be prescribed for each PWI by Sr.DEN/DEN.
In continuation of par 502 (4),
provided in the Manual, para 502(5) may be added as follows :
502(5) Joggling
of in-situ thermit welds :
A thermit welding done in-situ shall
be joggle fishplated with 4 clamps and supported on wooden blocks till tested
as good by USFD.
ADVANCE
CORRECTION SLIP No. 33 Dated. 06.08.1999
(Bd's
lr.No.99/CE-I/LX/80 dtd. 6.8.99).
A
new para no.922 may be added to chapter IX of IRPWM-1986 to read as under :-
922. Manning of the unmanned Level crossings
through Member of Parliament Local Area Development Scheme (MPLADS) : (1) The
manning of unmanned Level Crossings has been included in the list of works
covered under Member of Parliament Local Area Development Scheme (MPLADS). The funds for capital cost of construction
covering the cost of road, provision of lifting barrier, arrangement of water
and electricity, quarters for the gatemen, duty hut etc. will be provided by
Member of Parliament from MPLADS Fund and recurring maintenance and operation
cost will be borne by the Railways.
(2) Unmanned level crossings equal to number
of level crossings manned through Member of Parliament Local Area Development
Scheme, will be converted into manned level crossing at Railway's cost as
selected in consultation with Member of Parliament concerned.
(3) Preferably, selected unmanned Level
Crossings, should fall in the category I-V with priority given to Level
Crossings falling in Category-I followed by Category-II, III, IV, V. For Level crossings falling in the same
category on different routes, priority shall be given to A route followed by B,
C, D-Spl., E-Spl, D and E-routes.
(4) Divisional Railway Managers will liaison
with the District Authorities and the Hon'ble Member of Parliaments in
selecting the Level Crossings for manning.
On identification of the Level Crossings, Member of Parliament will send
his recommendations to the District Magistrate/ Dy.Commissioner for releasing
the funds. Railway will provide an
estimate for the work and any other details to the District Administration as
required. Departmental charges shall
not be levied on these works and supervision and establishment charges will be
kept to the minimum as provided in the case of similar Railway works. Separate accounts shall be maintained for
each work and `Utilisation Certificate' will be submitted to the District
Administration on completion of the work.
A
new par No.923 may be added to Chapter IX of IRPWM-1986 to read as under :-
923. Level
Crossings on National Highways/State Highways and Other Important roads.
(1) In case of National Highway/State Highways or their bypasses and important
city roads, no new Level Crossing to be provided and only grade separators can
also be considered.
(2) In case of other important roads, it is
preferable to provide grade separators.
However, depending upon the traffic density envisaged, manned Level
Crossings can also be considred.
(3) Relaxation
of the above (I) will require Board's prior approval.
ADVANCE
CORRECTION SLIP No. 32 Dated. 04.08.1999
The existing para 320(1)(a) may be
replaced to read as under :
Classification and
use of released material.- (a) After a section
of track has been renewed, the released material shall be carefully sorted out
so that greatest possible use may be made of them. They should then be classified by the Sr.Section Engineer (P.Way).
Tools and plant left over should also be classified and action taken on
their disposal.
A
new para 320(3) may be added, as below :
(3) Accountal
of released P.Way materials : (1) The quantity of released materials from
every work included for track renewal/gauge conversion will be based on
yardsticks for loss of weight to be fixed on the basis of data collected during
foot by foot survey. If there is more
than one work on the same route, near to each other and under similar ground
conditions, only one set of yardsticks would suffice.
2. List of materials likely to be released
will be prepared indicating the quantum of such materials separately as second
hand (SH) and scrap following the instructions given in para 320(2) above.
3. While second hand materials will be
indicated only in length/nos. in case of scrap materials, the accountal will be
as follows :
(i)
Rails - in length, then converted to weight.
(ii)
Sleepers - Nos. separately as whole and in parts and then converted to weight.
(iii)
Fittings & fastenings - by weight.
4. During foot by foot survey, actual observations
will be recorded jointly by PWI and ISA/Stock Verifier giving the percentage
loss of weight over the new component for each and every material likely to be
declared as `SCRAP'. This can be done
by actual weighment of few representative samples.
5. The yardsticks will then be approved by
the Sr.DEN/DEN personally based on the report duly test checked by AEN or
DEN. These will specify the maximum
percentage loss of weight for different components under different ground
conditions as per format given in the Annexure-3/1.
6. The conversion to weight in case of each
of the items for purpose of accountal will then be done by the Section Engineer
(P.Way) on the basis of the specified percentage loss of weight over the new
components. In case, however, some
abnormal variation of weight is observed after the materials have been released
and the percentage loss is more than that specified for that category, specific
justification will have to be recorded for the same by the Senior Section
Engineer (P.Way) and all such cases would have to be certified by DEN/Sr.DEN
after actual sample checking at site.
7. In case however, the actual loss after
release is seen to be lower than the yardstick the accountal will be done on
the basis of the actual.
8. After actual releases of materials, the
Section Engineer (P.Way) will take the releases on books on the basis of
summary sheet as per Annexure-3/2.
9. The sectional AEN will carry out test
checks to the extent of 20% of each item and make entries to this effect in the
summary sheet. The sectional DEN/Sr.DEN
will also carry out random checks to ensure that the category and weight of
releases are correct to the maximum possible extent.
10. The periodical returns for track
renewal/gauge conversions are to be submitted at the laid down periodicity as
per rules and the existing procedure for checking should be streamlined to
ensure that the returns are looked into detail in the AEN's office in nos. as
also their conversion in weight. The
returns will be specifically prepared on the basis of instructions given in
para-2 above.
11. As an internal check by the department, one
of the works accountants in the division with engineering department or with
construction department should be made responsible to carry out methodical
checks of all MAS accounts of track renewals/gauge conversion works.
12. In cases where the track work is to be done
by contractor, the list of released materials shall be jointly prepared on the
basis of field survey to be conducted by the Sr.Sec. Engineer (P.Way) and
contractors representative after the work has been awarded but before the
dismantling work is allowed to commence.
The contractor shall be bound to hand over the materials according to
the said agreed list and should be responsible for any shortages.
Annexure-3/1
LOSS
OF WEIGHT OF RELEASED SCRAP
(P.WAY
COMPONENTS)
DESCRIPTION
OF WORK : ______Railway
FOOT
BY FOOT SURVEY CARRIED OUT BY : ______Division
DATE
:
|
Sl. No |
Description of Material |
Weight of New item |
Max. % loss of weight on release |
Weight of released item |
Remarks |
|
1 |
Rails |
|
|
|
|
|
2 |
SLEEPERS : (a)
(a) Steel (b)
(b) CST-9 (c)
(c) Wooden |
|
|
|
|
|
3 |
FISH PLATE |
|
|
|
|
|
4 |
TIE BAR |
|
|
|
|
|
5 |
OTHER FITTINGS (a)
(a) Bearing Plates (b)
(b) ACP (c)
(c) ERC (d)
(d) Two way key, other fittings |
|
|
|
|
ANNEXURE-3/2
SUMMARY
OF P.WAY MATERIAL TO BE RELEASED.
NAME
OF WORK_______________________________________________
DIVISION_________________SECTION_____________PWI____________
DEN/SR.DEN___________________________________________________
PERIOD
OF EXECUTION OF WORK FROM (date) to (Date)____________
|
Km |
Category
of section |
Name
of material |
List of material to be released |
Remarks
for abnormality if any |
Sign.
of PWI |
Test
check by AEN |
Remarks |
|||
|
Serviceable
or scrap |
If scrap |
|||||||||
|
No/Length |
Rate
(WT) |
WT |
||||||||
|
|
|
|
|
|
|
|
|
|
|
|
ADVANCE
CORRECTION SLIP No. 31 Dated. 26.07.1999
(Bd's
lr.No.98/CE-II/TK/Misc.2 dt.26.7.99)
The following changes may be made in
the under-mentioned paras of IRPWM :-
Para 261
: The para shall read as follows :-
"Type of ballast in use - Stone
ballast shall be used on all lines including points and crossings."
Para 262
: The following may be replaced in the para -
"With
all types of sleepers 50mm gauge of square mesh sieve.
Under points and crossings 40mm gauge
on square
mesh sieve."
With the following :-
"As
per specifications issued from time to time."
Para
263(2)(a): The notes under the
recommended minimum depths of ballast below the bottom of the sleeper at the
rail seat shall read as follows :-
"Notes :-
1.
In case of SWR the recommended depth is 200mm.
2.
Whenever primary renewals are carried out even on E routes, the minimum depth
of ballast of 200mm shall be provided.
3.
Minimum depth of ballast under the rail seat of the sleepers shall be 150mm
except under PRC sleepers where it shall be 250mm.
4.
Wherever 22.1 t Axle load rolling stock is nominated to run the minimum depth
of ballast shall be 350mm."
IRPWM C/S No.30 dtd. 7.7.99 (Bd's letter No.98/CE-II/TS/1/pt. dt.7.7.99)
1.
The following may be added to para 202 (1) under Group B route:
(xvi)
Malda Town-Barsoi-New Jalpaiguri
2. The existing line under Group C of para
202(1) be replaced to read as `Suburban sections of Bombay, Delhi and
Calcutta'.
Group D Spl. Sections where the traffic density is
very high or likely to grow substantially in future and the sanctioned speed is
100 Km/h at present. The following
routes will fall under this category :-
(i)
Kharagpur-Midnapur-Adra
(ii)
Barkakana-Barwadih-Garwa Road
(iii)
Tundla-Yamuna Bridge
(iv)
Bolangir-Titlagarh
(v)
Gudur-Renigunta
(vi)
Anara-Chandil-Kandra-Sini
(vii)
Anuppur-Shahdol-Katni-Bina
(viii)
Ahmedabad-Viramgan
(ix)
Nagda-Ujjain-Maksi-Bhopal
(x)
Lucknow-Sultanpur-Zaffarabad-banaras
(xi) Delhi-Ghaziabad-Hapur-Moradabad
(xii)
Lucknow-Kanpur
(xiii)
Chapra-Hajipur-Barauni
(xiv)
RSD-Titlagarh-Vizianagaram
(xv)
Guntakal-Tornagallu
(xvi)
Udhna-Nandurbar-Jalgaon
Group E Spl
: Sections where traffic density is
very high or likely to grow substantially in future and present sanctioned
speed is less than 100 Km/h, the following routes will fall under this category
:
(iii)
Garwa Road-Sonnagar
(iv)
Tornagallu-Hospet
(v)
Panskura-Haldia
(vi) Talcher-Rajatgarh-Salegaon-Nergundi
(vii)
Cuttack-Paradeep
(viii) Radhakishorepur-Rajatgarh-Barang
(ix) Kapilas
Road-Salegaon
(x) Radhakishorepur-Machapur
(xi) Kirandul-Koraput
(xii) Rajkharswan-Dongaposi-Padapahar-Barajamda-Gua
(xiii)
Bondamunda-Bimlagarh-Barsuan-Kiriburu
(xiv)
Kandra-Gamharia
(xv)
Champa-Gevra Road
(xvi)
Marauda-Dallirajhara
(xvii)
Urkura-Sarona
(xviii)
Bhojudih-Mohuda G-C
(xix)
Chandil-Muri-Bokaro-Rajbera
(xx)
Diwa-Vasai Road
(xxi)
Padapahar-Banspani
(xxii)
Jharsuguda-Bolanikhandan
(xxiii)
Muri-Barkakana
(xxiv)
Talgoria-Bokaro City
(xxv)
Kota-Ruthiyai
3. List of `Q' routes at para 202(2)(a) be
substituted with the following list :-
(i) Delhi-Sarairohilla-Rewari-Ratangarh
(ii)
Rewari-Ringus-Phulera
(iii)
Ratangarh-Degana
(iv)
Ajmer-Ratlam-Khandwa
(v)
Jaipur-Phulera-Ajmer
(vi)
Bandikui-Agra Fort
(vii) Ahmedabad-Bhavnagar
(viii) Agra-Mathura-Bhojipura-Lalkuan
(ix)
Bhojipura-Lucknow
(x) Villupuram-Thanjavur-Tiruchchirappalli.
5. The list of R-1, R-2 & R-3 routes
shown under para 202(2)(b) be replaced with the following list :-
R-1 route
:
(i)
Gandhidham-Palanpur
R-2 route :
1. (i) Secunderabad-Mudkhed
2. (ii) Guntakal-Bellary
3. (iii) Guntakal-Villupuram
4. (iv) Tiruchchirappalli-Manamadurai-Virudunagar
R-3 route
:
1. (i) Madurai-Rameswaram
2. (ii) Virudunagar-Tenkasi
3. (iii) Dindigul-Pollachi
4. (iv) Ratangarh-Bikaner
Annexure 2/1 and 2/2
of P.Way Manual will stand corrected accordingly.
ADVANCE
CORRECTION SLIP No. 29 Dated. 07.07.1999
The following may be replaced in
supersession of Advance Correction Slip No.19 dated 18.11.98 Para 618 of IRPWM to read as under:-
618
Portable Accelerometers :
(1) General
:
OMS-2000 equipments are portable
accelerometers used for Oscillation monitoring using a portable accelerometer
and transducers converting the oscillations to electrical signals which can be
recorded electronically and processed on PC.
(2)
Operation :
The
OMS Accelerometer is kept in the cabin of locomotive or on the coach floor, as
close to the bogie pivot as possible.
It is preferable that same coach and the same vehicular position are
used in successive runs. The
accelerations recorded are transferred to electronic recorder and are readable
on the LCD display on real time basis.
The stored data can be downloaded on TMS Computer for maintenance
planning.
This
equipment measures the Track Performance by measurement of vehicle response in
terms of vertical and lateral accelerations. The real time output of the equipment is in the form of value of
peaks exceeding the limiting value, their location and Ride Index. These values are available for both vertical
and lateral accelerations.
(3)
Frequency of Recording :
A.
Broad Gauge :
Speed
above 100 Kmph Once every
month.
Others Once in two months.
B.
Metre Gauge :
Speed
above 75 Kmph. Once every
month.
Others Once in two months.
The above schedule is only a
guidance. Chief Engineers may vary it,
depending upon the availability of instrument and its use. For the time being A, B and C routes are to
be covered once a month and other routes can be covered as per capacity and
need.
(4)
Recording of Defects :
To
access the track quality, vertical and lateral acceleration peaks exceeding the
values as below are to be considered :
Broad
Gauge :
High
Speed Routes above 110 Kmph greater
than 0.15 g
On
A & B routes
Other
Routes upto 110 Kmph greater
than 0.2 g
Metre
Gauge greater than 0.2 g
(5)
Classification of Track Quality :
To
classify a continuous section's (PWI's jurisdiction/sub-division/division)
track quality, the following criteria to be used (average total number of peaks
per km.):
Very Good Good Average.
High
Speed Less than 1.0 1 - 2 Greater
than 2
Others Less than 1.5 15-3.0 Greater
than 3
The above criteria are for judging the
quality of track. However, if the
average number of peaks of vertical and lateral accelerations exceeding 0.30g
is more than 0.25 per km. or more than one in any particular kilometre, the
track will need attention. All
locations where peaks of lateral and vertical accelerations exceed 0.25 g, the
track will have to be attended to urgently.
The
existing contents of para 252(3) along with Annexure 2/9 of IRPWM 1986, may be
deleted and substituted with the following :-
(3) Reference to
Manual for Ultrasonic Testing of Rails and welds, August-1998.
Detailed
instructions for Ultrasonic Testing of Rails and welds are contained in the
Manual for Ultrasonic Testing of Rails and Welds, Auigust, 1998 which may be
referred to as an Annexure to this Manual.
It is very important that instructions contained thereon are carefully
studied by the Permanent Way Officials connected with the laying and
maintenance of track.
The
frequency for USFD testing of rails in service on A, B & D routes of BG
(keeping in view the traffic density and speed) is given in the table below :
|
Route |
Frequency |
|
|
(a)
(I) A,B & D routes of BG |
After
passage of 8 GMT subject to a Maximum interval of six months as per table
below : |
|
|
|
GMT |
Testing frequency |
|
|
|
|
|
|
Upto
15 GMT |
6 months |
|
|
15-30 |
4 months |
|
|
30-45 |
3 months |
|
|
above
45 |
2 months |
|
|
|
|
|
(ii)
If in a kilometre total REM & IMR defects detected and actual fractures
exceed 1 per km between two successive testing. |
The
frequency which caused defect generation rate more than 1 per km. should be
doubled. |
|
(b)
For other section (C & E of BG and
MG sections) Chief Engineers may apply this frequency at their discretion or
continue with conventional frequency of testing.