INDIAN RAILWAYS SCHEDULE OF DIMENSIONS (B.G,) 1973

SCHEDULED – II

CHAPTER I-R GENERAL

RECOMMENDED DIMENSIONS

*  Spacing of Tracks

*  Formation Single Line

*  Formation, Double Line

*  Gauge on curves

*  Speed on Carves

*  Transition Curves

*  Sleepers

*  Ballast

 

The following are recommended dimensions, which are generally considered good practice, the adoption of which will lead to very desirable uniformity on Indian Railways, but they are not to be treated as standards, a departure from which requires sanction. The clearances to fixed structures and distance centre to centre of tracks prescribed in item 13 of Chapter I, Schedule I for tunnels & Bridges should also be adopted for all structures and no only for tunnels and through Bridges at the time of new construction, or additions/alterations to the existing structures. If, however, in cases where 3660mm stock is not going to be introduced and adoption of these dimensions would entail heavy expenditure, an administrative reference should be made to the Board individually in each case before execution of the work for adopting less clearances. ( Part of para replaced vide CS#    )

Under Chapter II-R Station Yards are also included some dimensions which will facilitate future expansions.

 

Chapter I R General

 

Where it can be done without appreciable increase of cost, it is desirable to make all clearances greater than those precribed in Schedule I.

 

Spacing of Tracks

1R

Minimum distance centre to centre of track

4725 mm

Formation Single Line :

2R

Minimum width in embankment

6100 mm

3R

Minimum width in cutting (excluding side drains)

5490 mm

Formation, Double Line

4R

Minimum width in embankment

10820 mm

5R

Minimum width in cutting (excluding side drains)

10210 mm

Note— (a) For standard C lines, 1R & 2R may be reduced to 5030 mm. 3R & 4R to 9750 mm.

(b) On a curves, the width of formation for double line should be increased by the amount shown in column 9 of the Appendix.  

Gauge on curves

6R

The gauge on curves shall be as followers :—

 

 

Exact gauge

Up to curves of 4º 438 M radius

 

6mm. slack

Above curves of 4º 438 M radius

 

Speed on Carves

 

 

7R

The maximum speed permissible for rooling stock in good order on fully ballasted first class track fur transitioned curves should be determined by following formula:

 

 

Where                     V    =      Maximum speed in kilometre per hour,

                              R    =      Radius of curve in metres,

 

                         or

 

 

Where                       V1    =      Maximum speed in miles per hour,

                                 R1    =      Radius of curve in feet.

For non-transitioned curves the maximum speed should be 4/5th of V & V 1.

The above speeds are subject to the maximum speed permitted on the section of Railway concerned.

The value of super elevation is often  over estimated. It is suggested that the  super-elevation   provided should suit the maximum speed at which the majority of trains may reasonably be expected to travel on the curve.

 

7R.

(i) Maximum super-elevation

165 mm

7R

(ii) Maximum deficiency permissible in cost
calculated for speed of the fastest train in the
section.

75 mm

Transition Curves—

8R.

Except between points  and  crossings, the ends of circular curves should be properly eased by transition approaches.

 

The Chief Engineer of each Railway may adopt in each case the method of inserting transition curves which he may consider most suitable.

 

(See Technical Papers Nos. 300 and 301, also quarterly Technical Bulletin Vol. 4 No. 43, October, 1936)

 

9

SLEEPERS

 

9-R

Maximum length

2745 mm

10-R

Maximum breadth

254 mm

11-R

Minimum depth

127 mm

 

Note :-  (a) For deodar and other soft wool sleepers, used with learning plates, a section of 229 mm. x 152 mm. would probably be better.

(b)              For Standard ‘C’ lines, half round sleepers may be used for section given in Technical Paper No. 169.

 

12-R  

The following minimum sleeper densities are recommended for adoption on  primary tracts :-

 

 

 

(i) 1300 sleepers per Km. Where the traffic density exceeds 4.5 million G.Te. Km (Gross Tonne Kilometre) per Km. Per annum, but does not exceed 6 million G.Te. km. Per Km. per annum.

 

or

 

2100 sleepers per mile, Where the traffic density exceeds 4.5 million G.T.M. (Gross Tonne Mile) per mile Per annum, but does not exceed 6 million G.T.M. Per mile per annum.

 

(ii) 1450 sleepers per Km. Where the traffic density exceeds 6 million G.Te. Km. per annum but does not exceed 10 million G.Te. km. Per Km. per annum.

 

or

 

2350 sleepers per mile, Where the traffic density exceeds 6 million G.T.M. (Gross Tonne Mile) per mile Per annum, but does not exceed 10 million G.T.M. Per mile per annum.

 

(iii) 1550 sleepers per Km. Where the traffic density exceeds 10 million G.Te. Km Per Km. per annum.

 

or

 

2500 sleepers per mile, Where the traffic density exceeds 10 million G.T.M. per mile Per annum.

 

Note-

(a)          Actual number of sleepers may very slightly depending on the length of rail.

On secondary and tertiary track, lesser sleeper density may be provided.

(b)         On bridges where cross sleepers rest directly on longitudinal girders, the sleepers are to be spaced so as to allow not more than 510 mm. between the edges of adjacent sleepers and are to be not less than 152 mm. deep exclusive of any notching which may be required to allow for cover plates, camber etc.

(c)          The length of cross timbers laid on longitudinal girders may be reduced to not less than 305 mm greater than the distance outside to outside of the girder flanges.

The minimum length of steel sleepers should be the distance outside to outside if girder flanges subject to a minimum 2440 mm.

Bridges—For all Gauges,

Note-It is advisable that guard rail should be provided on bridges where a derailment would be likely to result in serious damage to the structure e.g.. through spans. Check rails are not necessary except where a sharp curve crosses a bridge. Where cross sleepers whether wooden or steel are provided, the guard rail should be fastened to each sleeper.

 

 

Ballast—

The following widths and depths of ballast are recommended.

13-R

(i) Width of ballast at level of foot of rail         

3350 mm

 

(ii) Depth of ballast below sleeper.

203 mm

 

Note .—{a) On lines carrying heavy or fast traffic, a compacted layer of  suitable blanketting material of adequate thickness is desirable.

 

 

(b) It must be understood that the recommendation of 11 R and 12 R are for good formation. On poor formation either the number of sleepers or depth of ballast or both may have to be increased. In this connection  Section D-9 and D-10 of Technical paper No. 245 may be referred to.

 

 

Rails :-

The axle loads specified in this and the following item are for general guidance only. The actual axle load to he pei milted will depend on the type of rail (flat fooled or bull headed), extent of wear, modulas of track, wheel arrangements of the vehicle and the hammer blow etc.

 

 

14-R

Maximum axle loads at 105 km. per hour speed for rolling stock except 4 wheeler in good order and on well maintained road for different section of rails, provided the rail his not lost more than 5% of its original section and that the amount of ballast and numbers of sleeper is a adequate (See Item 11 R and 12 R).   

 

 

Section of Rail (weight when new)

Axle Load including (weight of wheels & axle)

57.0 kg/metre

28.5 tonnes

49.5 kg/metre

25.5 tonnes

44.5 kg/metre

23.0 tonnes

42.0 kg/metre

21.0 tonnes

39.5 kg/metre

19.0 tonnes

37.0 kg/metre

17.5 tonnes

 

 

15-R

Maximum axle loads on "Standard 'C- Railways for speeds limited to 32 km. ph. provided the rail has not lost more than 5% of its original section.

 

 

 

Section of Rail (weight when new)

Axle Load including (weight of wheels & axle)

 

 

37.0 kg/metre

23.0 tonnes

 

 

 

16-R             Extra vertical clearance under overhead structures and overhead equipment in electrified sections.

                   Allowance to be made for raising of track to permit modern track structure to be introduced                      275mm.

         

                    Note:      On lines proposed to be electrified on 25KV AC system necessary provision should be made in over head structures and overhead equipment, if necessary, by using longer traction overhead equipment masts to permit possible raising of the track by 275 mm in future to cater for increased ballast cushion, larger sleeper thickness and deeper rail section. ( New item 16-R introduced vide CS#10)

 

INDEX OF

CONTENTS

CORRECTION SLIPS